You can subscribe to our email list to receive these work notices electronically, based on the areas of interest to you.
Filter by area:
Tuesday 24 May to Friday 3 June 2022 24 05 2024
Out of hours works, Wilsons Lane, Sunbury (PDF, 261.7 KB)
- The site at 35 Wilsons Lane, Sunbury will be used for the delivery, storage and assembly of materials, worker amenities and construction vehicle parking
- Delivering large steel beams to the site that will form support structures for the new rail bridge and road underpass
- Constructing rail infrastructure, including pipes and conduits that will be used during construction of the new rail bridge
- Works involve the use of a small crane, light towers, hand tools and other construction machinery.
Sunbury Station precinct
Sunbury Station precinct
Ongoing to early 2022 10 12 2022
Sunshine Road, Tottenham construction update (PDF, 208.6 KB)
- Excavation and conduit installation works
- Substation building works
- Car park extension and site establishment works
- Landscaping and reinstatement works
- Ongoing long-term closure of the Sunshine Road car park at Tottenham station.
Tottenham to Footscray
Tottenham to Footscray
20 – 23 May 2022 20 05 2022
Out of hours works from Sunshine to Watergardens (PDF, 622.9 KB)
- Installing overhead wiring between Albion and St Albans stations
- Installing signalling equipment along the rail corridor between Sunshine and Watergardens stations
- Preparatory works to enable upcoming train track upgrades near the new Albion substation
- Connecting cables to the train tracks near the new St Albans Road substation
- Works will involve the use of track drilling equipment, hand tools and other construction machinery.
Project-wide
Project-wide
9 May to 17 July 09 05 2022
Site establishment, signalling works and car park closures at Watergardens Station (PDF, 595.0 KB)
Signalling works
- Installing communications and signalling services in the commuter car park on Watergardens Circuit Road
- Accessing a pit in the car park to install new cables underground
- These works involve the use of hand tools and construction vehicles.
Site establishment and car park closures
- To enable track upgrades that will take place during an upcoming scheduled closure of the Sunbury Line, we will establish a temporary work site in the northern commuter gravel car park on Watergardens Circuit Road
- The site will be used for the delivery, storage and assembly of materials, worker amenities
and construction vehicle parking - Installing temporary fencing and levelling the ground in preparation for construction machinery and storage use
- Additional commuter car parking on Watergardens Circuit Road will be temporarily closed to facilitate construction activities and bus replacement services during the scheduled closure of the Sunbury Line
- In addition to normal construction hours, these sites will be used to support out of hours works.
Calder Park to Sydenham
Calder Park to Sydenham
7 – 8 May 2022 07 05 2022
Out of hours works, Calder Park (PDF, 464.8 KB)
- Overhead wiring upgrades, service installations, and track works
- Installing new communications and power services
- Maintenance work within the rail corridor to the existing tracks and rail signalling equipment
- Works will involve the use of a saw cutter, excavator, trucks, hand tools and other construction machinery.
Calder Park to Sydenham
Calder Park to Sydenham
Sunbury Station precinct monthly construction update, May (PDF, 510.0 KB)
- Service installations near the O’Shanassy and Station Street roundabout
- Construction works near the Target shopping complex
- Site preparation and level crossing removal works
- Site establishment at Shields Street
- Service installations and soil testing near Sunbury Station
- Site preparation and partial commuter car park closure.
Sunbury Station precinct
Sunbury Station precinct
Ongoing to 16 May 2022 27 04 2022
Substation and car park reopening works on Sunshine Road, West Footscray (PDF, 100.1 KB)
- Ongoing installation of cables and electrical equipment inside the substation building near Tottenham Station
- Removing the project compound that has supported substation extension works
- Reopening the Sunshine Road commuter car park on Monday 16 May 2022.
Out of hours works
- Installing new communications and signalling services
- Installing devices that help detect passing trains
- These works involve the use of hand tools only.
Tottenham to Footscray
Tottenham to Footscray
2 to 31 May 2022 21 04 2022
Site establishment and overnight works at the Jacksons Hill substation, 2 to 31 May 2022 (PDF, 89.4 KB)
Site establishment activities
- Establishing a small project site compound at the Jacksons Hill substation near Lark Court
- Installing temporary fencing, worker amenities and a laydown area for the storage of construction materials
Out of hours works
- Out of hours works in the rail corridor at the Jacksons Hill substation
- Excavating trench routes and installing new underground cables between the substation and rail corridor
- Non-destructive digging to investigate ground conditions and confirm the area is free of underground services
- Connecting cables and electrical equipment that will supply power to the Sunbury Line
- Using a small crane to help remove and dispose of overhead electrical structures within the rail corridor.
Sunbury Station precinct
Sunbury Station precinct
26 April to 10 May 2022 19 04 2022
Sunshine to Ginifer signalling works (PDF, 3.8 MB)
- Replacing a pit lid in the Sunshine Station commuter car park on Sun Crescent
- Sawing through asphalt to remove the lid
- Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services. NDD uses pressurised water to break up and vacuum soil to expose assets and services without damaging them
- Works will involve the use of a saw cutter, excavator, tipper, hand tools, a NDD truck and other construction vehicles.
- Removing old signalling equipment at the St Albans Road substation
- Installing new communications and signalling services
- NDD to investigate ground conditions and confirm the area is free of underground services
- Works will involve the use of a road saw, excavators, tippers, hand tools, a NDD truck and other construction vehicles.
Keilor Downs to St Albans
Keilor Downs to St Albans
8 to 30 April 2022 08 04 2022
Construction works between Sydenham and Calder Park (PDF, 465.1 KB)
Service installations
- Installing communication, drainage, and power services in the rail corridor along Sydenham Road
- Non-destructive digging (NDD) works to expose underground services
- Installing new emergency fire services and fencing that will be accessible to the Metropolitan Fire Brigade.
Footpath extension
- Concreting works to extend pathways in the Watergardens Station car park
- This will involve removing and replacing the car park entry and existing concrete islands along Watergardens Circuit Road
- NDD works to expose underground services.
Landscaping works
- Revegetation and planting near the rail corridor along Victoria Road
- By planting new plants along the rail corridor, we’re preventing soil erosion near newly constructed drains.
Calder Park to Sydenham
Calder Park to Sydenham
Ongoing to late April 2022 05 04 2022
Construction works between St Albans and Calder Park (PDF, 421.2 KB)
- Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services. NDD uses pressurised water to break up and vacuum soil to expose assets and services without damaging them
- Excavating a hole for a parking signpost in the Regan Street car park
- Installing a bike rack in the Regan Street car park
- Underground boring works along East Esplanade and through the Keilor Plains Station commuter car park to upgrade electrical cables
- Works involve the use of excavators, hand tools, a NDD truck and other construction vehicles.
Calder Park to Sydenham
Calder Park to Sydenham
4 April to 10 June 2022 04 04 2022
Landscaping and drainage installation works, St Albans (PDF, 92.4 KB)
Landscaping activities
Ongoing to Friday 10 June 2022
- Using a small crane to complete the installation of the decorative screen around the substation site
- Installing pathways and native landscaping around the new substation building
- All native plants and grasses have been chosen to reflect the natural environment in the area
- Decorative rocks and a tree trunk will be included as part of the landscaping
- Concrete mixers will be on site at times to pour the concrete that will form the new pathway and gutter.
Sewerage pipe upgrade works
Monday 4 April to Friday 10 June 2022
- Upgrading sewerage pipes on Bent Street, between Willaton and Rhodes streets
- Underground boring works will take place from the new substation on Willaton Street and travel underneath Bent Street to the first roundabout
- Excavation works to create launch and retrieval shafts for the underground boring machinery will be required
- These works may not occur each day during this period.
Stormwater installation works
Late April to mid-May 2022
- Installing new underground stormwater pipes underneath Willaton Street and connecting them
to the existing stormwater system - Temporarily closing Willaton Street during
weekdays, between Austin and Kingsley streets - Using excavators to dig underground and non-destructive digging (NDD) to expose
underground services.
Keilor Downs to St Albans
Keilor Downs to St Albans
Sunbury Station precinct monthly construction update, April (PDF, 217.1 KB)
- Service installations near the O’Shanassy and Station Street roundabout
- Signalling equipment room and fence installation works near the Target shopping complex
- Retaining wall works near BP
- Capping beam, fence installation and drainage works
- Site establishment and rail equipment deliveries
- Service installations near Sunbury Station.
Sunbury Station precinct
Sunbury Station precinct
21 March - 1 April 2022 21 03 2022
Drainage works on Station Street, Sunbury (PDF, 138.4 KB)
- Non-destructive digging (NDD) to investigate ground conditions and confirm the location is free of underground services
- Installing drainage services underneath Station Street
- Excavating and saw cutting asphalt and concrete
- Trenching works
- These works involve the use of excavators, a jackhammer, a saw cutter, a NDD truck and other construction machinery.
Sunbury Station precinct
Sunbury Station precinct
Ongoing to April 2022 04 03 2022
Substation works, Sunshine Road, West Footscray (PDF, 104.3 KB)
Substation works and car park closure
Ongoing to late April 2022
- Installing building amenities, cables and electrical equipment inside the substation building near Tottenham Station
- Ongoing closure of the Sunshine Road commuter car park at Tottenham Station until late April 2022. Up to 36 car spaces remain closed.
Landscaping and reinstatement works
Saturday 5 March to Friday 8 April 2022
- Footpaths, asphalt and vegetation will be
reinstated around the new substation building - Installing new substation fencing with gates and
security features.
Light pole installation works
Wednesday 9 March to Monday 28 March 2022
- Installing new light poles, bollards and fencing
- Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
- Constructing foundations for the new light poles that will supply lighting to the rail corridor and substation.
Tottenham to Footscray
Tottenham to Footscray
Sunbury Station precinct monthly construction update, March (PDF, 350.5 KB)
- Service installations and tree removal near the O'Shanassy Street and Station Street roundabout
- Post and panel retaining wall works near Target and BP
- Capping beam, drainage and backfill works
- Out of hours rail deliveries
- Service installations and tree removal near Sunbury Station.
Sunbury Station precinct
Sunbury Station precinct
McNab Avenue, Footscray (PDF, 266.6 KB)
- Ongoing long term closure of McNab Avenue
- Ongoing pedestrian access changes
- Electrical equipment installation works
- Out of hours works near Footscray Station
- Site demobilisation works.
Tottenham to Footscray
Tottenham to Footscray
21 February to late April 2022 21 02 2022
Substation works at Sydenham Road, Delahey (PDF, 145.8 KB)
- Using excavators and non-destructive digging (NDD) to expose underground services
- Operating a small crane to install a new underground concrete pit and connecting it to conduits that will service the new substation building
- Construction machinery will access the rail corridor via Carbine Way.
Albion to Sunshine
Albion to Sunshine
February to September 2022 01 02 2022
Construction works for 55A Raes Road, Sunbury (PDF, 527.8 KB)
- A temporary storage site will be established at 55A Raes Road, Sunbury
- The site will be used for the delivery, storage and assembly of materials, and construction vehicle parking
- Installing temporary fencing and levelling the ground in preparation for construction machinery and storage use
- In addition to normal construction hours, this site will be used to support out of hours works as required
Sunbury Station precinct
Sunbury Station precinct
10 January to mid 2022 23 12 2021
Keilor Downs to St Albans
11 January to mid 2022 23 12 2021
Substation works on St Albans Road, St Albans (PDF, 84.2 KB)
- Using excavators and boring machines to dig underground
- Installing new underground conduits which will be used to pull electrical cables through
- Installing building amenities, cables and electrical equipment inside the substation building
- Using a small crane to lift electrical equipment into the substation building
- Footpaths and vegetation will be reinstated around the new substation building
- Installing fencing, gates and a new driveway along St Albans Road
- Installing a decorative screen to the exterior of the substation building.
Keilor Downs to St Albans
Keilor Downs to St Albans
Ongoing to late 2022 09 12 2021
Construction works on Wilsons Lane, Sunbury (PDF, 262.0 KB)
- A temporary storage site will be established at 35 Wilsons Lane, Sunbury. The site is being used for the delivery, storage and assembly of materials, worker amenities and construction vehicle parking
- In addition to normal construction hours, this site will be used to support out of hours works as required
- The temporary site will be used for plant, equipment and material storage
Sunbury Station precinct
Sunbury Station precinct
Ongoing until March 2022 06 09 2021
Substation works, Calder Park (PDF, 466.2 KB)
- Non-destructive digging to investigate ground conditions and confirm the area is free of underground services.
- Installing communications and power services
- Removal and delivery of materials
- Using a concrete truck to pour a large concrete slab that will safely hold machinery during major works scheduled for late 2021 and early 2022.
Calder Park to Sydenham
Calder Park to Sydenham
Ongoing until March 2022 06 09 2021
Substation services installation works, Sydenham (PDF, 416.5 KB)
- Installing drainage and water services that will support the substations operations
- Installing communications and power services
- Non-destructive digging to investigate ground conditions and confirm the area is free of underground services
- Installing a fence to safely contain new facilities.
Calder Park to Sydenham
Calder Park to Sydenham