You can subscribe to our email list to receive these work notices electronically, based on the areas of interest to you.

Filter by area:

When
What

December 2021 to January 2022 31 12 2021

Willaton Street, St Albans construction update, December 2021 and January 2022 (PDF, 249.7 KB)

  • Excavation, underground boring works and powerline upgrades
  • Underground electrical equipment installation and tree removal works
  • Sewerage installation works
  • Landscaping reinstatement works

Keilor Downs to St Albans

Keilor Downs to St Albans

11 December 2021 11 12 2021

Craning activities and out of hours works on McNab Avenue, Footscray (PDF, 94.0 KB)

  • Using a truck to transport the palm tree safely back to McNab Avenue
  • Setting up a crane on McNab Avenue next to the substation site
  • Lifting and reinstating the palm tree that was removed from McNab Avenue in February 2021
  • Support beams will be installed to help keep the tree upright after it has been replanted

Tottenham to Footscray

Tottenham to Footscray

29 to 30 November 2021 29 11 2021

Out of hours delivery of a pre-built substation, St Albans Road, St Albans (PDF, 107.3 KB)

  • Overnight delivery of a pre-built substation building on an oversize truck with escort vehicles
  • Using hand tools to secure the substation building to the on-site foundations

Keilor Downs to St Albans

Keilor Downs to St Albans

November 2021 15 11 2021

Sunbury Station precinct monthly construction update, November 2021 (PDF, 175.4 KB)

  • Service relocations
  • Piling activities
  • Retaining wall construction
  • Installing communications and signalling services
  • Drainage, excavation and installation works in the rail corridor

Sunbury Station precinct

Sunbury Station precinct

November to early 2022 15 11 2021

McNab Avenue, Footscray construction update, December 2021 to January 2022 (PDF, 271.0 KB)

  • Substation building and cable pulling works
  • Landscaping and garden bed reinstatement works
  • Site establishment and non-destructive digging works
  • Excavation and underground boring works
  • Ongoing long term closure of McNab Avenue
  • Ongoing pedestrian access changes

Tottenham to Footscray

Tottenham to Footscray

November 2021 to early 2022 03 11 2021

Substation delivery and site works at Sydenham Road, Delahey (PDF, 198.9 KB)

  • Out of hours delivery of a pre-built substation
  • Sewerage installation works
  • Excavation and underground boring works
  • Landscaping and reinstatement works

Keilor Downs to St Albans

Keilor Downs to St Albans

23 October to 29 November 2021 23 10 2021

Craning activities and vegetation removal works on Sunshine Road, Tottenham (PDF, 88.8 KB)

  • A crane will be set up in the Tottenham station car park next to the existing substation
  • Overnight the crane will lift and install steel panels and roofing materials that will form the substation building
  • Removing five small trees to allow for the construction of a new driveway onto Sunshine Road

Tottenham to Footscray

Tottenham to Footscray

October 2021 to early 2022 04 10 2021

McNab Avenue, Footscray construction update October 2021 (PDF, 273.5 KB)

  • Substation building and electrical installation works
  • Excavation and non-destructive digging works
  • Underground boring works
  • Landscaping and garden bed reinstatement works

Tottenham to Footscray

Tottenham to Footscray

October 2021 to early 2022 04 10 2021

Signalling and substation works, between Maribyrnong River and Tottenham (PDF, 1.4 MB)

  • Continuing the installation of communications and signalling services
  • Installing cables and conduits along the rail corridor
  • Installing trackside signalling equipment including location boxes that house signalling and cables on existing signalling structures
  • Installing building amenities, cables and electrical equipment inside the substation building
  • Removing vegetation along Sunshine Road, near the existing Tottenham substation
  • Removing five small trees to allow for the construction of a new driveway onto Sunshine Road
  • Upon completion of works, re-planting of vegetation will occur along Sunshine Road

Tottenham to Footscray

Tottenham to Footscray

October 2021 to early 2022 04 10 2021

Substation works, St Albans Road, St Albans (PDF, 126.5 KB)

  • Installing drainage pipes, stormwater pits and conduits that will service the new substation building
  • Using cement mixers to pour concrete and create the base slab for the substation foundations
  • Excavating and installing two precast concrete slabs that will support two new light poles
  • Non-destructive digging to investigate ground conditions and confirm the area is free of underground services
  • Excavating trench routes and installing cables and conduits underground
  • Overnight delivery of a pre-built substation building on an oversize truck with escort vehicles

Keilor Downs to St Albans

Keilor Downs to St Albans

16 September to late November 2021 16 09 2021

Substation works on Talmage Street, Albion and reduced parking at Albion station (PDF, 99.7 KB)

  • Using saws to cut through asphalt in the Albion station car park, to take samples of the soil beneath the ground
  • Excavation works are required in the Albion station car park to facilitate upgrades to underground cables and to install new electrical supply equipment
  • Underground boring works will take place from the new substation on Talmage Street and travel underneath the rail corridor to the Albion station car park

Albion to Sunshine

Albion to Sunshine

Ongoing until late 2021 09 09 2021

Substation works on Willaton Street, St Albans (PDF, 110.6 KB)

Substation foundation works

  • Using excavators to dig underground and prepare the site for the new substation
  • Installing drainage pipes, stormwater pits and conduits that will service the new substation building
  • Using cement mixers to pour concrete and create the base slab for the substation foundations

Out of hours work

  • Installing new communications and signalling facilities
  • Non-destructive digging to investigate ground conditions and confirm the area is free of underground services.
  • Excavating and installing cables and conduits
  • Trenching for pit installation

Keilor Downs to St Albans

Keilor Downs to St Albans

Ongoing until March 2022 06 09 2021

Substation services installation works, Sydenham (PDF, 416.5 KB)

  • Installing drainage and water services that will support the substations operations
  • Installing communications and power services
  • Non-destructive digging to investigate ground conditions and confirm the area is free of underground services
  • Installing a fence to safely contain new facilities

Calder Park to Sydenham

Calder Park to Sydenham

Ongoing until March 2022 06 09 2021

Substation works, Calder Park (PDF, 466.2 KB)

  • Non-destructive digging to investigate ground conditions and confirm the area is free of underground services.
  • Installing communications and power services
  • Removal and delivery of materials
  • Using a concrete truck to pour a large concrete slab that will safely hold machinery during major works scheduled for late 2021 and early 2022

Calder Park to Sydenham

Calder Park to Sydenham