You can subscribe to our email list to receive these work notices electronically, based on the areas of interest to you.

Filter by area:

When
What

29 July to late 2021 29 07 2021

Substation works and tree removal on Willaton St (PDF, 87.1 KB)

  • Using chainsaws and excavators to remove eight trees from along Willaton Street to prepare for site establishment
  • Using excavators to dig underground and prepare the site for the new substation
  • Overnight delivery of a pre-built substation building on an oversize truck with escort vehicles
  • Upgrading sewerage pipes on Bent Street, between Willaton and Rhodes streets
  • Some trees and minor vegetation will be removed to facilitate these works.

Keilor Downs to St Albans

Keilor Downs to St Albans

Ongoing until September 2021 26 07 2021

Sunbury Station precinct out of hours works, service installations, and traffic changes (PDF, 1.0 MB)

  • Ongoing relocation of essential services to prepare the area for the removal of the Gap Road level crossing
  • Non-destructive digging (NDD) to investigate pre-existing underground services along Gap Road, Station, Evans and Horne streets
  • Excavating trench routes and pits to install underground services.

Sunbury Station precinct

Sunbury Station precinct

Late July to late 2021 25 07 2021

Substation works and vegetation Sydenham Road late July to late 2021 (PDF, 79.5 KB)

  • Using excavators to remove vegetation from along Sydenham Road to prepare for site establishment
  • Using excavators and boring machines to dig underground and prepare the site for the new substation
  • Overnight delivery of a pre-built substation building on an oversize truck with escort vehicles
  • Upgrading sewerage pipes on Sydenham Road and McNicholl Way
  • Some trees and minor vegetation will be trimmed and removed to facilitate these works.

Keilor Downs to St Albans

Keilor Downs to St Albans

20-24 July 20 07 2021

Boom gate installation at Watergardens station 20-24 July 2021 (PDF, 406.8 KB)

  • Installing two boom gates near Watergardens station, north of the Melton Highway
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Installing piles that will support the foundations of the new boom gates

Albion to Sunshine

Albion to Sunshine

July 2021 08 07 2021

St Albans Road July construction update (PDF, 2.7 MB)

  • Site establishment works
  • Traffic barrier installations works
  • Concrete pouring works
  • Long term temporary closure of a section ofthe St Albans Road walking and cycling path
  • Delivery of a pre-built substation building.

Keilor Downs to St Albans

Keilor Downs to St Albans

2 to 7 July 2021 02 07 2021

Out of hours works between Tottenham and Albion station 2 to 7 July 2021 (PDF, 4.1 MB)

  • 24-hour and out of hours construction works during a scheduled shutdown of the Sunbury Line
  • Installing communications and power services to support the Sunbury Line’s new high capacity signalling system
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Excavating trench routes and installing cables and conduits underground
  • Trenching and foundation works at Tottenham station
  • Installation of structures to support raised boarding platforms at Albion station
  • Transporting, lifting and connecting new overhead wiring structures along the rail line
  • Removing redundant structures and foundations along the rail corridor

Tottenham to Footscray

Tottenham to Footscray

17 to 25 July 2021 02 07 2021

McNab Avenue, Footscray craning and temporary road closures 17 to 25 July 2021 (PDF, 178.8 KB)

  • Setting up a crane on McNab Avenue next to the future substation site
  • Lifting and installing pre-cast concrete walls that will form the substation building
  • Temporarily extending the closure of McNab Avenue, while craning activities and deliveries take place.

Tottenham to Footscray

Tottenham to Footscray

2 to 9 July 2021 02 07 2021

Sunbury Station precinct July construction update (PDF, 1.1 MB)

  • Site and service investigations
  • Culvert extension works
  • 24-hour construction works in the rail corridor between Albion and Sunbury from 9pm Friday 2 July to 5am, Friday 9 July
  • Sunbury station works
  • Tree and vegetation removal
  • Service relocations along Gap Road, Station Street and Evans Street
  • Westbound outer lane closure along Gap Roadand Station Street.

Sunbury Station precinct

Sunbury Station precinct

2 to 9 July 2021 02 07 2021

Out of hours works between Calder Park and Sunbury 2 to 9 July 2021 (PDF, 154.6 KB)

  • 24-hour and out of hours construction works along the rail corridor during a scheduled shutdown of the Sunbury Line
  • Installing communications and power services to support the Sunbury Line’s new high capacity signalling system
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Excavating trench routes and installing cables and conduits underground
  • Transporting, lifting and connecting new overhead wiring structures along the rail line
  • Removing redundant structures and foundations along the rail corridor.

Calder Park to Sydenham

Calder Park to Sydenham

2 to 9 July 2021 02 07 2021

Out of hours works between Albion and Watergardens stations 2 to 9 July 2021 (PDF, 621.4 KB)

  • 24-hour works during a scheduled shutdown of the Sunbury Line
  • Installing communications and power services to support the Sunbury Line’s new high capacity signalling system
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Excavating trench routes and installing cables and conduits underground
  • Removing redundant cables and structures along the rail corridor
  • Transporting, lifting and connecting new overhead wiring structures along the rail line

Albion to Sunshine

Albion to Sunshine

2 to 7 July 2021 02 07 2021

Out of hours works and traffic changes at Middle Footscray station 2 to 7 July 2021 (PDF, 1.5 MB)

  • Asphalting on the platforms at Middle Footscray station. Works will include the use of an asphalting truck, excavators, a motorised wheelbarrow for removing spoil
  • 24-hour and out of hours construction work during a scheduled shutdown of the Sunbury Line
  • To support these activities, we will be accessing the rail corridor with construction vehicles and machinery at the following locations in Footscray:
    • John Street, Footscray
    • Windsor Street, Footscray

Tottenham to Footscray

Tottenham to Footscray

2 to 7 July 2021 02 07 2021

Out of hours works at Leunig Place 2 to 7 July 2021 (PDF, 1.0 MB)

  • 24-hour and out of hours construction works along the rail corridor during a scheduled shutdown of the Sunbury Line
  • Accessing the rail corridor with construction vehicles and machinery on a 24-hour basis
  • Using the temporary site for material storage.

Tottenham to Footscray

Tottenham to Footscray

July 2021 01 07 2021

Calder Park to Sydenham monthly construction update July 2021 (PDF, 951.3 KB)

  • Ongoing substation works at Calder Park
  • Ongoing expansion works at the train stabling facility at Calder Park
  • Installation of new communications, power and signalling infrastructure along the rail corridor
  • Removal and replacement of expired rail assets
  • 24-hour construction works in the rail corridor between Watergardens station and Calder Park from 9pm, Friday 2 July to 5am, Friday 9 July.

Calder Park to Sydenham

Calder Park to Sydenham

July 2021 01 07 2021

Maribyrnong to Tottenham monthly construction update July 2021 (PDF, 1.5 MB)

  • Installing new signalling and communications services
  • 24-hour construction works in the rail corridor between Maribyrnong River and Tottenham station from 9pm, Friday 2 July to 5am Monday 5 July
  • Out of hours construction works each night from 8pm to 3am, Monday 5 July to Wednesday 7 July.

Tottenham to Footscray

Tottenham to Footscray

30 June to 9 July 2021 30 06 2021

Out of hours works and car park closures at Keilor Plains station 30 June to 9 July 2021 (PDF, 419.8 KB)

  • Installing communications and power services to support the Sunbury Line’s new high capacity signalling system
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Excavating trench routes and installing cables and conduits underground
  • Removing redundant cables and structures along the rail corridor
  • Cable pulling along the rail corridor
  • Transporting, lifting and connecting new overhead wiring structures along the rail corridor.

Keilor Downs to St Albans

Keilor Downs to St Albans

Ongoing to late 2021 29 06 2021

Talmage Street substation works ongoing to late 2021 (PDF, 96.4 KB)

  • Using excavators to dig underground and install drainage pipes that will service the new substation building
  • Using cement mixers to pour concrete and create the base slab for the substation foundations
  • Using a crane to lift and install the concrete wall panels that will form the substation building
  • Using trucks to deliver the pre-built substation wall panels to Talmage Street

Albion to Sunshine

Albion to Sunshine

19 to 24 June 2021 19 06 2021

Temporary car park closure at Ginifer station June 2021.pdf (PDF, 468.7 KB)

  • Restoring a section of the Ginifer station car park
  • Asphalting, compacting and line marking a section of the car park damaged during recent construction activities
  • Works will involve the use of an asphalting truck, a compactor, construction vehicles and a spray can for line marking.

Keilor Downs to St Albans

Keilor Downs to St Albans

June 2021 to mid-2022 15 06 2021

Site establishment and walking cycling path closure on St Albans Road (PDF, 816.5 KB)

  • Site establishment
  • Long term temporary closure of a section of the St Albans Road walking and cycling path
  • Site investigations and cable installation works
  • Delivery of a pre-built substation building.

Keilor Downs to St Albans

Keilor Downs to St Albans

4 to 25 June 2021 04 06 2021

Keilor Plains out of hours works, service installation and car parking closures (PDF, 111.4 KB)

  • Installing communications and power services to support the Sunbury Line’s new high capacity signalling system
  • Non-destructive digging (NDD) to investigate ground conditions and confirm the area is free of underground services
  • Transporting, lifting and connecting new overhead wiring structures along the rail line
  • Removing an existing pit and excavating a new trench route to install underground services
  • Installing new cables and conduits underground and removing redundant cables and structures
  • Undertaking works on the existing overhead wiring structures in the Keilor Plains station car parks along Regan Street and East Esplanade

Keilor Downs to St Albans

Keilor Downs to St Albans

June 2021 01 06 2021

Sunshine Road, Tottenham June construction update (PDF, 232.8 KB)

  • Substation building foundation works
  • Vegetation removal
  • Excavation and non-destructive digging (NDD) works
  • New driveway installation works
  • Ongoing long-term closure of the Sunshine Road car park at Tottenham station
  • Services installations and out of hours works

Tottenham to Footscray

Tottenham to Footscray

June 2021 01 06 2021

Maryibyrnong River to Tottenham, June construction update (PDF, 1.5 MB)

  • Installing new signalling and communications services
  • 24-hour construction works in the rail corridor between Maribyrnong River and Tottenham station from 9pm, Friday 11 June to 5am, Monday 14 June.

Tottenham to Footscray

Tottenham to Footscray

June 2021 01 06 2021

Sydenham to Calder Park construction update June 2021 (PDF, 950.3 KB)

  • Ongoing substation works at Calder Park
  • Ongoing expansion works at the train stabling facility at Calder Park
  • Installation of new communications, power and signalling infrastructure along the rail corridor
  • Removal and replacement of expired rail assets
  • 24-hour construction works in the rail corridor between Watergardens station and Calder Park from 9pm, Friday 11 June to 5am, Monday 14 June.

Calder Park to Sydenham

Calder Park to Sydenham

Mid-May 2021 to mid-2022 15 05 2021

Substation site establishment on Willaton Street, St Albans (PDF, 2.0 MB)

  • Site establishment
  • Tree removal
  • Site investigations and cable installation works
  • Delivery of a pre-built substation building.

Keilor Downs to St Albans

Keilor Downs to St Albans

Ongoing to late 2021 15 05 2021

Substation works on Talmage Street, Albion (PDF, 105.4 KB)

  • Using excavators and boring machines to dig underground and install communications and power services in excavated trenches
  • Using excavators to dig underground and prepare the site for construction of the substation
  • Using excavators to dig underground and install drainage pipes required for the new substation building.

Albion to Sunshine

Albion to Sunshine

Mid-May 2021 to mid-2022 15 05 2021

Substation site establishment on Sydenham Road, Delahey (PDF, 799.5 KB)

  • Site establishment
  • Site investigations and cable installation works
  • Delivery of pre-built substation

Keilor Downs to St Albans

Keilor Downs to St Albans

14 April to June 30 2021 08 04 2021

Power upgrades, Albion to Calder Park (PDF, 122.6 KB)

  • Installation of new communications, power and signalling infrastructure along the rail corridor
  • Excavation and non-destructive digging works
  • Works at electrical substation sites along the rail corridor between Albion and Calder Park

Keilor Downs to St Albans

Keilor Downs to St Albans

March 2021 to late 2022 14 03 2021

Tottenham substation extension works (PDF, 1.1 MB)

  • Establishing a project site compound including worker amenities, project staff car parking and a laydown area for the storage of construction materials

Tottenham to Footscray

Tottenham to Footscray

From mid-January to late 2021 01 01 2021

Albion site establishment works (PDF, 84.9 KB)

  • Establishing a project site compound including worker amenities, project staff car parking and a shipping container for the storage of construction materials
  • Ongoing closure of the heritage substation private car park to late 2021

Albion to Sunshine

Albion to Sunshine

From late November 2020 to late 2021 30 11 2020

Site establishment works, Talmage Street, Albion (PDF, 1.3 MB)

  • Establishing a project site compound including worker amenities, project staff car parking and a shipping container for the storage of construction materials
  • Long-term closure of the heritage substation private car park for up to 12 months

Albion to Sunshine

Albion to Sunshine

From 23 November 2020 to early 2022 23 11 2020

McNab Avenue, Footscray site establishment and road closure (PDF, 100.3 KB)

  • Establishing a project site compound including worker amenities, staff car parking and a laydown area for the storage of construction materials
  • Ongoing closure of McNab Avenue until early 2022

Tottenham to Footscray

Tottenham to Footscray

From late October 2020 to early 2022 31 10 2020

Footscray substation construction update (PDF, 1.1 MB)

  • Establishing a project site compound including worker amenities, staff car parking and a laydown area for the storage of construction materials
  • Long-term closure of McNab Avenue for up to 18 months

Tottenham to Footscray

Tottenham to Footscray

From 14 September 2020 to late 2020 14 09 2020

West Footscray cross street site mobilisation (PDF, 104.5 KB)

  • Establishing a project site compound including worker amenities and project staff car parking

Tottenham to Footscray

Tottenham to Footscray