Gap Road reopened to traffic on 30 September 2022 after a 4-month closure to build the new rail bridge and road underpass.

Landscaping and other minor works will continue into 2023.

Visit Sunbury Line Upgrade work notifications to stay up to date on all upcoming works and disruptions.

Construction progress

We have completed major works to remove the level crossing for good and free up congestion in the heart of Sunbury. This involved:

  • removing the boom gates
  • building the new rail bridge
  • installing a First Nations designed artwork on the rail bridge
  • excavating 25,000 cubic metres of soil
  • building the road underpass.