30 January 2026

We’re upgrading Boronia Station and building a new landscaped plaza on Dorset Road to deliver a modern and accessible precinct for the community.

What we’re doing

Throughout February, we’ll continue setting up the temporary laydown area on the northern corner of Erica Avenue and Orchid Avenue. During this time, we’ll also:

  • relocate underground drainage and utilities for the new protective services office on Lupton Way
  • start demolition works at 251 and 253 Dorset Road, to make space for the new landscaped plaza

Our usual working hours are Monday to Friday 7am to 6pm, and Saturday 7am to 3pm. We’ll make every effort to complete these works on schedule, however dates are subject to change.

What to expect

You may notice:

  • an increase in construction activity, machinery, vehicles and workers
  • an increase in noise, dust and vibration near works areas. Our team will have controls in place to reduce and monitor these impacts
  • reduced speed limits and traffic management in place around our works: please plan ahead in case of delays
  • carparks in Lupton Way will be used at times for works vehicles.

Before building demolition works begin, asbestos identified at 251 and 253 Dorset Road will be safely removed in line with strict health and safety guidelines. We’ll follow environmental controls in line with legislative requirements, to ensure the ongoing safety of both our workers and the community.


Changes to the way you travel

Please follow signage and detours. Traffic management will be in place during works to safely guide you through the area. We will update directly impacted residents and traders in advance.

Road

  • Lupton Way closed to vehicles for 5 days in late February. Detour via Dorset Road.
  • Intermittent road closure and lane closures around works areas on Lupton Way at times until late 2026.
  • Intermittent road closures near the corner of Erica and Orchid avenues at times until late 2026.

Parking

  • Northern corner of Erica and Orchid Avenues informal parking closed at times until late 2026.
  • Around 4 car spaces closed outside 251 and 253 Dorset Road for 3 days in late February.

Pedestrian

  • Pedestrian access between Chandler Road and the Lupton Way bend closed for 5 days in late February.
  • Eastern station entrance closed for 5 days in late February. Western station entrance remains open. Access via the southern footpath on Lupton Way.
  • Footpath closure outside 251 and 253 Dorset Road for 3 days in late February. Detour via pedestrian crossings and the east side of Dorset Road.