20 June 2024
We’ve removed the level crossing at Bedford Road, Ringwood, while construction continues to remove the level crossing at Dublin Road, Ringwood East which will make Ringwood level crossing free in 2024, a year ahead of schedule.
While our major construction blitz to remove the Bedford Road level crossing is complete, we are continuing works to finalise the new Bayswater power station.
Continuing through July 2024, we’ll continue works to install new permanent fencing around the power station site as well as some finishing works around the site.
Works will include:
- Replacing existing kerbs, footpath and driveway around the new power station site
- Relocating a water meter
- Installing fencing and gates
- Minor landscaping
- Car park finishing works
Works will occur during the day from 7am to 6pm, Monday to Friday within the Bayswater power station site.
Impacts to parking
Station Street
- A small section of footpath and on-street parking along Station Street (near the power station site) will be closed for footpath and kerb replacement works from Monday 1 July to Friday 12 July.
Bayswater Station commuter carpark
- Approx. 30 carparks closed for Bayswater power station works until July 2024.
What to expect
- Presence of workers, trucks and construction equipment with some noise from construction machinery.
- Please be aware that works can sometimes take longer than expected or need to be rescheduled due to weather and other factors outside of our control.
More information
- If you have any questions about these works, please call us on 1800 105 105 or email contact@levelcrossings.vic.gov.au.
- Subscribe for regular project updates.
- Visit our Facebook page for the latest project news.
- Text RINGWOOD to 0428 387 902 for SMS alerts.