30 March 2022

The Victorian Government is removing the level crossing on Glenroy Road and building a new Glenroy Station. By Saturday 14 May, the level crossing will be gone for good with trains running to the new station.

In April and May, we will be completing works in the rail trench as well as preparing the new station to open. We will start carparking and landscaping works in Dowd Place on the western side of the new rail line, ready for the area to open in mid-September.

From 26 April to 14 May, we will be undertaking 24 hour works to remove the level crossing. The new Glenroy Station will open to passengers from 7 May. Works to remove the boom gates will continue on Glenroy Road, with 24 hour works until 14 May.

Construction activities

Over the coming months, the following activities will be taking place:

  • Construction of the new roundabout at the intersection of Hartington and Nelson streets
  • Works to complete the Glenroy Road bridge, barriers and screening
  • Connecting the train line and rail infrastructure in the rail trench
  • Installing fixtures, utilities and staff and passenger facilities at the new station
  • Traffic management will be in place during these works. Please follow any signage and instructions from traffic management when travelling around the area.

Every effort will be made to complete these works on time, however dates are subject to change.

Key construction dates

1 April

  • Hartington Street roundabout open

3 April

  • Dowd Place closes

26 April

  • Glenroy Road closes
  • 24 hour works to remove the level crossing

7 May

  • New Glenroy Station open. Access from Hartington Street only

Mid September

  • Glenroy Station completely open – access from Hartington Street and Post Office Place
  • Dowd Place car park open

Changes to how you move around the area

  • Hartington, Nelson and Marlborough streets will experience road and lane closures at times until Thursday 31 March for roundabout works.
  • Glenroy Road will be closed at the level crossing from Tuesday 26 April and will reopen on Saturday 14 May, with the level crossing removed. Detours will in place via Gaffney Street in the south and Camp Road to the north. Pedestrian access across the level crossing will be maintained at all times.
  • Buses will replace trains on the Craigieburn line between Tuesday 26 April and Friday 6 May.
  • The new Glenroy Station will open to passengers from first service on Saturday 7 May. Initial access will be from Hartington Street only.
  • From Saturday 7 May 141 car spaces will open on at the northern end of Hartington Street.
  • Dowd Place will close to traffic from Sunday 3 April until mid-September. Pedestrian access will remain with access to the existing Glenroy Station available until Thursday 26 April.