30 November 2026

Site investigations that are underway are continuing to late December to better understand local conditions and inform the design of the rail bridges and the new Seaford Station.

What we’re doing

We’re locating underground services and completing surveying on Station Street, Railway Parade, Seaford Station car park and the Caulfield-Frankston Rail Trail between Clovelly Parade and Station Street until Friday 18 December.

What to expect

  • Intermittent lane closures, walking and cycling path disruptions and Seaford Station car space temporary closures. Traffic management will be in place to guide you around the area
  • Works between 7am and 6pm, Monday to Friday and nightworks between 6pm to 6am
  • Increased noise, vehicles and workers in the area

We’ll make every effort to complete works on schedule; however, dates are subject to change.


Changes to the way you travel

Road

Station Street

  • Closed to vehicles between Chapman Avenue and Railway Parade 10pm to 4am each night, Monday 14 December to Wednesday 16 December, 11pm, Thursday 17 December to 5am, Friday 18 December:
    • Traffic will be detoured via Nepean Highway, Seaford Road and Railway Parade. Please see map below.
    • Vehicle access to and from Seaford Station western car park will be maintained with traffic management in place.
  • Lane closures at times 9am to 3pm each weekday until Friday 18 December.

Railway Parade

  • Lane closures at times 9am to 3pm each weekday until Friday 18 December.

Parking

Seaford Station western car park

  • Up to 14 car spaces closed from 9am, Friday 13 November to 3pm, Friday 18 December.
  • Up to 20 car spaces closed at times from 7am to 6pm each weekday and one night between Monday 7 December and Friday 18 December.

Pedestrians and cyclists

Caulfield-Frankston Rail Trail between Clovelly Parade and Station Street

  • Traffic management in place at times for pedestrians and bike riders 7am to 6pm each weekday until Friday 18 December.

Detour map

Works map Seaford Nov 2026

More information