31 July 2023
We’re making the Frankston Line level crossing free by removing all 27 of the dangerous and congested level crossings by 2029 and building 17 new stations, improving safety, reducing congestion and allowing more trains to run more often.
We’ve removed the dangerous and congested level crossings at Neerim Road and Glen Huntly Road and will soon open the new Glen Huntly Station to passengers with better facilities and more services from early August.
24-hour construction blitz is expected to finish next week
During the 2 month construction blitz we:
- excavated 160,000 cubic metres of material to create the rail trench
- poured 25,000 cubic meters of concrete to form the base and walls of the trench
- installed the new Glen Huntly Station buildings
- installed the bridge beams at Neerim and Glen Huntly roads
- finished the Neerim Road and Glen Huntly Road bridges over the trench
- installed the new tram infrastructure
- installed new signalling, overhead wiring and infrastructure within the trench
- installed new ballast, rail and rail infrastructure.
Upcoming works
Throughout August, construction activities will continue, but the volume will decrease significantly as we gradually demobilise workers and machinery across the project area.
During August, we’ll:
- close Neerim Road between 7pm and 7am for 3 nights to complete road resurfacing works. We’ll provide more information including exact dates in a separate notification prior to these works
- continue to build the new Glen Huntly Station, including bricklaying to create the archway, station fit-out and installation of the new lifts.
What to expect
While we work, you will notice:
- 24-hour works within the station precinct, below Glen Huntly Road
- works during standard construction hours in the project area, 7am to 6pm Monday to Friday and 7am to 3.30pm on Saturdays
- workers, trucks, vehicles, and equipment in the area
- minor impacts to local roads in and around the project area
- traffic management in place to help guide motorists and pedestrians through the area safely.
Upcoming travel changes – road
Please be aware that dates may change due to weather and other factors outside of our control. For SMS updates about last-minute changes, text "GH" to 0429 839 892.
Derby Crescent
- Intermittent lane closure and parking changes with traffic management in place between Clifton Street and Queens Avenue, local access only until late August.
- No parking on Epsom Street until Monday 31 July.
Dorothy Avenue
Existing southbound lane closure until September 2023. Intermittent single lane closures
- Road closure between Hawson Avenue and Rothschild Street until Monday 31 July.
- Southbound lane closure between Malvolio Street and Rothschild Street from Monday 31 July to mid September.
Etna Street (South-west car park)
- Intermittent lane closure and parking changes with traffic management in place until late 2023.
Huntly Street
Existing road closure at Station Place until October 2023.
- No parking on north side of road, permit parking only on south side of Huntly Street until Monday 31 July.
James Street
- Intermittent lane closures and parking changes with traffic management in place until late 2023.
Leamington Crescent and Lord Street
- Intermittent lane closures and parking changes with traffic management in place until late August.
MacGowan Avenue
- Pedestrian crossing closure, detours via Neerim Road, Glen Huntly Road or Woodville Avenue until Monday 31 July.
Neerim Road
- No entry from Neerim Road into Queens Avenue until Monday 31 July.
- Road closure at night between Watson Grove and Heath Drive for 3 nights in mid August, 7pm to 7am.
- Local access only between Heath Drive and Booran Road, and Watson Grove and Grange Road
- East-west pedestrian access maintained
- Dates of closure will be notified separately in advance
North-west carpark (Esprit Apartments)
- No access from Glen Huntly Road until late 2023.
Rosedale Avenue
- No parking on north side of road, permit parking only on south side of Rosedale Avenue until Monday 31 July.
Royal Avenue
Existing northbound lane closure between Glen Huntly Road and Wattle Avenue until late 2023.
- Station works, road reinstatement and kerb works until Monday 31 July.
- Road closure between Glen Huntly Road and Rosedale Avenue
- Southbound lane open between Glen Huntly Road and Wattle Avenue
- Drainage system upgrade works until late 2023.
- Road closure between MacKay Avenue and Oakleigh Road, detours in place via Woodville Avenue
- Road closure at intersection of Royal Avenue and MacKay Avenue
- No on-street parking between MacKay Avenue and Oakleigh Road
- EE Gunn Reserve access via Dorothy Avenue/ Woodville Avenue
Station Place
- Road closure between Watson Grove and Glen Huntly Road until October.
Queens Avenue
Existing pedestrian detour in place until October 2023.
- Road and footpath closure between 12 Queens Avenue and Neerim Road, no entry into Neerim Road until Monday 31 July.
Wattle Avenue
- Pedestrian crossing closure, detours via Neerim Road, Glen Huntly Road or Woodville Avenue until Monday 31 July.
Woodville Avenue
- Drainage system upgrade works until late 2023.
- Road closure from Dorothy Avenue to Oakleigh Road
- No through access to Royal Avenue
- Access to EE Gunn Reserve via Dorothy Avenue
Upcoming travel changes – rail
- Cranbourne and Pakenham lines until early August.
- Buses replace trains every weekend on sections of the line until late July
- Visit the PTV website or call 1800 800 007
- Frankston and Stony Point lines until early August:
- Glen Huntly Station is closed
- Buses replace trains on sections of the Frankston and Stony Point lines
- Visit the PTV website or call 1800 800 007
- Caulfield Station car park closed until Friday 28 July:
- The Station car park off Normanby Road is closed
- Alternative all-day parking available at East Malvern Station. The car park is located off Sylvester Crescent, Malvern East
- Accessible parking closed. Passengers requiring accessible parking are advised to use either Ormond or Carnegie stations
Stay up to date
- Sign up for email updates
- SMS GH to 0429 839 892 for text message alerts
- Call us on 1800 105 105 or email contact@levelcrossings.vic.gov.au
- Translation service – For languages other than English, please call 9209 0147