28 April 2026
We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale to deliver faster and safer journey times by building new rail bridges. We’ve already closed the Bear Street, Mordialloc level crossing and are building a new Mordialloc Station.
What we’re doing
During May, works will continue ahead of the new Mordialloc Station opening and trains running on the new rail bridges from Thursday 21 May. We’ll also permanently remove the dangerous and congested level crossings at McDonald Street, Mordialloc and Station Street, Aspendale.
Major construction in May
From Thursday 30 April to Thursday 21 May, our crews will work around the clock to prepare the new station and elevated rail bridges to open to passengers. We will:
- remove existing rail infrastructure, including tracks and the boom gates
- install the remaining station and rail infrastructure needed for trains to run on the elevated rail
- complete and open the new Pine Crescent link road in Aspendale, connecting Station Street to the Nepean Highway
- complete road and kerb reinstatement, including sections of the new station car parking.
What to expect
McDonald Street and Station Street level crossing closures
Detours are via White Street and Edithvale Road. Allow extra travel time and expect increased congestion.
Mordialloc Creek temporary closures
Boat access under Mordialloc Creek rail bridge will close at times between Thursday 30 April and Thursday 21 May. We’ll install signage at the boat ramp ahead of closure and notify any affected mooring holders and other community groups in advance. Access to the nearby pedestrian bridge and paths will be maintained.
Continuous day and night works
You may notice increased noise, vibration, lighting and heavy vehicle movements across the area. We’ll be in touch with directly impacted residents and traders in advance.
Additional lane, footpath, and road closures
Temporary lane, footpath or road closures may be required while we work, including after Thursday 21 May. Traffic management and detours will be in place as required. Conditions may change at short notice, so please follow signage and allow extra time. If you need additional support getting around or more information, please call us on 1800 105 105 or you can email us.
Changes to the way you travel
Road closures and detours may change at times. Traffic management will be in place to safely guide you through the area. Please follow signage and allow extra time.
Mordialloc
McDonald Street
- Level crossing removal and road reinstatement from Thursday 30 April to Thursday 21 May:
- Full road closure between Main Street Service Road and Albert Street. Detours via White Street and Edithvale Road.
- Pedestrian access across the rail line may change during this time. Please follow signage and detours.
Right of Way south of McDonald Street
- Mordialloc Station precinct and carpark works from Tuesday 21 April to late September:
- Local access only.
Right of Way north of McDonald Street
- Level crossing removal from Monday 20 April to late June:
- Carpark closed.
Albert Street
- Mordialloc Station northern entry works and oversized deliveries from Tuesday 21 April to Thursday 21 May:
- Road closed 24/7 between McDonald Street and Lewis Street.
- Traffic management in place.
- Oversize deliveries at times from Tuesday 28 April to Thursday 21 May:
- Full road closure between McDonald Street and Powlett Street. Detour via Barkly Street.
- Construction of the new rail bridge and Mordialloc Station, new bus bays and pedestrian crossings and oversized deliveries until late April:
- One way traffic (southbound) from McDonald Street to Bear Street.
- Construction of the new Mordialloc Station precinct, landscaping, footpath and commuter car parking from Thursday 21 May to late September:
- One way traffic (southbound) from Ashmore Avenue to Lewis Street.
Como Parade West and Nepean Highway
- Construction access and works near rail bridge at times from Thursday 30 April to Sunday 17 May:
- Short term lane closures under rail bridge between White Street and High Street.
Aspendale
Nepean Highway
- Road profiling, asphalt, and line marking for the new intersection from Friday 1 to Tuesday 31 May, 7pm to 7am each night:
- Nepean Highway reduced to one lane at times between Watkins Street and just south of Hearle Avenue.
- Residents will continue to have access to their driveways. Please expect delays and plan ahead.
- Link road construction Thursday 30 April to Thursday 21 May:
- Lane closures at times between Alfred Street and Kiandra Close.
- Oversize deliveries at times until late 2026:
- Lane closures at times between Alfred Street and Kiandra Close.
Station Street
- Level crossing removal from Thursday 30 April:
- Station Street level crossing permanently closed.
- Local access maintained to Scope Disability Services.
- Oversized deliveries, installing rail infrastructure, constructing link road and landscaping at times until late 2026:
- Station Street closed at times between Attenborough Road and Eulinga Avenue. Local access maintained.
- Level crossing removal works from Thursday 30 April to Thursday 21 May:
- Station Street closed between the level crossing and Attenborough Road. Pedestrian access over the rail line will be maintained and locations may change. Follow signage and detours.
Rail
Frankston and Stony Point Line
- Buses replace trains:
- Between Cheltenham, Frankston, and on the Stony Point Line from 10.30pm, Thursday 30 April to 8.30pm, Monday 18 May.
- Between Moorabbin, Frankston, and on the Stony Point Line from 8.30pm, Monday 18 May to last service, Wednesday 20 May.
Pedestrian
Station Street
- Level crossing closed from Thursday 30 April to Thursday 21 May:
- Detour southbound via Lyle Grove (1.3km), northbound via Longbeach Trail (450m) or Mordialloc Station area (900m).
More information
- Sign up for email updates
- Text MRD to 0429 839 892 to receive SMS updates
- Call us on 1800 105 105 or email levelcrossings@bigbuild.vic.gov.au
- For assistance accessing this information in other languages, please call 9280 0780
- Visit our Level Crossing Removal Project Facebook page