20 August 2025
We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale by building new rail bridges. We have now also closed the Bear Street level crossing in Mordialloc to vehicles and are building a new Mordialloc Station.
What we’re doing
Major construction is continuing throughout September as we continue to build foundations for the new rail bridges.
During September, we will:
- continue piling, earth and civil works
- install new underground services and rail systems in Mordialloc and Aspendale
- carry out electrical and signal upgrades, install cables and remove overhead wires in the rail corridor.
There may be temporary utility service interruptions to local homes. Utility companies are responsible for notifying customers of any interruptions. Please contact your utility provider if you have any questions.
Upcoming night works
To complete essential piling works, we’ll work during the day and at night in the rail corridor until 6pm, Sunday 14 September between McDonald and Bear streets, Mordialloc.
During this time, you may notice:
- an increase in construction activity, machinery, vehicles and workers in the area
- additional lighting at night, directed away from residential properties where possible
- noticeable construction noise and vibration in the area.
Overnight oversized deliveries
To minimise disruptions to daytime traffic, oversized machinery and materials will be delivered overnight by trucks and cranes via the McDonald Street and Station Street level crossings. During these times, you may notice a moderate increase in noise and lighting:
- 1.30am to 4am, Tuesday 2 September to Friday 5 September
- 1.30am to 4am Monday 8 September to Friday 12 September
- 10pm to 5am, Tuesday 16 September to Friday 19 September
- 1.30am to 4am, Monday 22 September to Thursday 25 September
There will be intermittent road closures and some delays. Local access will be maintained. We’ll be in touch with directly impacted residents and traders in advance.
Travel and access changes at Mordialloc Station
From Friday 29 August to mid 2026, we'll close Platform 2 at Mordialloc Station. Trains will run in both directions from Platform 1 to keep passengers moving and reduce the need for replacement buses while we build the rail bridges and new station. While these changes are in place, you can expect:
- minor timetable changes on the Frankston Line, with some reduced services
- the majority of Mordialloc Station car parks will remain closed.
Passengers can access Platform 1 via McDonald, Bear or Main streets. Passengers are encouraged to plan ahead and check timetable information at Transport Victoria.
Station Street, Aspendale changes
No standing zones will be in place close to intersections to help safe turning movements with traffic management in place during works to help guide motorists.
Changes to the way you travel
Mordialloc
McDonald Street
- Intermittent lane closures between Albert Street and Nepean Highway/Main Street Service Road throughout September. Local access maintained. Pedestrian access changes at times, please follow signage.
Bear Street
- Pedestrian access changes until late 2026. Please follow signage.
Albert Street
- Intermittent road and lane closures between Lewis Street and Bear Street throughout September. Local access maintained. Please follow signage and detours in place. We will be in touch with directly affected residents.
Aspendale
Nepean Highway
- Intermittent lane and parking closures with traffic management in place between Station Street and Kara Grove until 2026.
Station Street
- Intermittent road closures between Station Street level crossing and Eulinga Avenue under traffic management until late 2026. Please follow signage and detours.
Public transport
Frankston Line
- Buses replace trains between Cheltenham and Carrum from 10pm to last service each night, Tuesday 16 September to Thursday 18 September.
Mordialloc Station
- Platform 2 and station underpass closed from Friday 29 August. All train services will depart from Platform 1 (To City / To Frankston). Pedestrian access to Platform 1 via McDonald, Bear and Main Street.
Altered Frankston Line timetable
- Trains will run to an altered timetable from Friday 29 August to mid 2026. Timetable information is available at Transport Victoria or via passenger information displays at your station.
We’ll make every effort to complete these works on schedule, however dates are subject to change.
More information
- Sign up to email updates on our website.
- Text MRD to 0429 839 892 to subscribe to SMS alerts.
- Email us at contact@levelcrossings.vic.gov.au or call us on 1800 105 105, 24 hours a day.