27 March 2025

We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale by building new rail bridges. We’re also removing and closing the Bear Street level crossing in Mordialloc and building a new Mordialloc Station.

What we’re doing

During April, we will:

  • Complete earthworks and piling in the rail corridor and on Albert Street, Mordialloc between McDonald and Bear streets.
  • Construct hardstand in the rail corridor near Pine Crescent, Aspendale, to support heavy machinery for piling (drilling) works.
  • Install new rail services in Mordialloc and Aspendale.
  • Continue site establishment at 4 Bear Street, Mordialloc.
  • Continue vegetation removal and install safety fencing along the rail corridor.
  • Temporarily relocate the Mordialloc Station bus interchange from the station (west) side of Albert Street to the other side of the road to make room for ongoing works near the station. Signs will be in place to guide you.

Utility companies will relocate services, including electricity, gas and water to make way for construction works. Temporary service interruptions to private properties may occur, and your utility provider will notify you ahead of time.


McDonald Street closure

McDonald Street in Mordialloc will remain closed between Albert Street and the Nepean Highway until mid-April for continuing civil upgrade works on the McDonald and Main Street intersection. For more information please see our Mordialloc disruption map.

Mordialloc Creek and the Governor Road boat ramp temporary closures

Public access to Mordialloc Creek will be closed from the Governor Road boat ramp to west of the Mordialloc Creek rail bridge over 3 non-consecutive days in April and May, while we bore under the creek to install underground rail services.

We’ll install signage at the boat ramp ahead of closure dates and notify community groups and any affected moorings holders in advance. These works will not affect access to the nearby pedestrian bridge or paths.


What to expect

Throughout April, you should expect changes to road conditions, parking, and pedestrian paths. You may notice an increase in construction workers and machinery, including moderate noise and vibration at times. Please expect delays on Nepean Highway in both directions, predominantly southbound, and allow extra travel time.

We’ll work 7am to 6pm on weekdays and 7am to 3pm on Saturdays. We’ll also work 24/7:

  • until mid April to complete McDonald Street works
  • from 8.30pm, Friday 16 April to last service Sunday 18 May in the rail corridor.

If we need to work outside of these times, we’ll let the community know in advance.


Changes to the way you travel in Mordialloc

McDonald Street

  • Closed between Albert Street and Main Street Service Road until mid April.
  • Pedestrian detour remains in place from mid April to late 2026.

Main Street Service Road South (McDonald Street to Bear Street)

  • No access from McDonald Street – use Main Street/Nepean Highway entry until mid April.
  • Temporary closure of car parks until mid April.

Main Street Service Road (north of McDonald Street)

  • No vehicle access – pedestrian access only from 9am to 3pm from Monday 7 April to Wednesday 16 April. We’ll notify impacted properties directly ahead of time.

Mordialloc Creek

  • Closed from the Governor Road boat ramp to west of the Mordialloc Creek rail bridge from 7am to 5pm at times in April and May. Please see the signage at boat ramp.

Changes to the way you travel in Aspendale

Station Street

  • Parking lane (southbound) closed between Attenborough Road and Eulinga Avenue until late 2026.
  • Bicycle lane (southbound) permanently closed between Attenborough Road and Eulinga Avenue. When the project is complete, cyclists will use the new shared use path next to the rail line.

Mordialloc Creek carpark

  • Closed until late 2026.  3 car parking spaces to remain open for  access to boats.

Frankston and Stony Point lines

  • Buses will replace trains between Cheltenham, Frankston and Stony Point stations from 8.30pm, Friday 21 March to last service, Sunday 23 March.

Mordialloc Station car parks

  • Changes to commuter parking and access at times from Monday 2 February to early May. Visit the PTV website for more information.

Bus routes

  • view information about ongoing changes to local bus routes and bus stops at the PTV website.

For the safety of the community and our workers, traffic management will be in place throughout the area with short stops to pedestrians and vehicles at times while machinery and trucks are moving through the area.