25 May 2025

We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale by building new rail bridges.

We’re also removing and closing the Bear Street level crossing in Mordialloc and building a new Mordialloc Station.


What we're doing

During June, we will:

  • undertake earthworks, piling and rail bridge construction in the rail corridor in two locations:
  • Albert Street, Mordialloc between McDonald Street and Bear Street
  • Station Street, Aspendale between Attenborough Road and Ruvina Street
  • complete drainage works along Station Street, Aspendale
  • complete essential utility, drainage and road reinstatement works on McDonald Street, Mordialloc
  • continue installing new rail services in Mordialloc and Aspendale
  • continue vegetation removal and install safety fencing along the rail corridor
  • construct a temporary road on Station Street, Aspendale between the level crossing and Attenborough Road, in preparation for sewer realignment works in July
  • remove power poles and overhead wires along Albert Street.

Utility companies will continue relocating services (electricity, gas and water) to make way for construction works. Temporary service interruptions to private properties may occur, and your utility provider will notify you ahead of time.

To find out more about piling and how we build a rail bridge, view our Mordialloc and Aspendale – how we build the rail bridge fact sheet.


McDonald Street closure

McDonald Street will be closed from 5am, Monday 16 June until early July for the completion of essential utility, drainage and road reinstatement works.

Please follow signage and detour via White Street or Bear Street.


Station Street changes

In late June, we’ll build a temporary road west of Station Street, between the level crossing and Pine Crescent, to maintain traffic flow during sewer realignment and installation works in July and August.

From Thursday 3 July until early August the temporary road will be in use, and Attenborough Road will be closed at the intersection of Station Street to maintain safe traffic flow in the area.

Parking on Attenborough Road will remain available. Temporary weekday no-standing zones will be installed on Pine Crescent and Pine Court to enable safe traffic movements.

No standing will apply from Monday 21 July until early August during school pick up and drop off times. Residents can park in these streets at other times.

Please expect delays and plan ahead. Pedestrian access will be maintained.


What to expect

Throughout June, there will be changes to road conditions, parking, and pedestrian access. You may notice an increase in construction workers and machinery, including moderate noise and vibration at times. Noise and vibration will continue to be closely monitored to ensure levels remain within safe and acceptable limits.

Pedestrian access changes will be in place on McDonald Street and in Mordialloc Creek Reserve throughout June and July. Intermittent lane closures will be in place on Nepean Highway, Bear Street and Station Street.

We’ll work 7am to 6pm on weekdays and 7am to 3pm on Saturdays. We’ll also work 24/7 from 8.30pm, Friday 27 June to last service, Sunday 29 June in the rail corridor. If we need to work outside of these times, we’ll let the community know in advance.


Changes to the way you travel

Head to our interactive map for the full list of disruptions in your area.

Rail

Frankston and Stony Point lines

  • Buses replace trains between Cheltenham, Frankston and Stony Point from 11pm, Friday 27 June to last service, Sunday 29 June.

Road

McDonald Street

  • Eastbound lane closed between Main Street Service Road and the level crossing for 2 days in early June.
    • Local access maintained for Main Street Service Road (north of McDonald Street).
  • Road closed between Albert Street and Nepean Highway/Main Street Service Road from 5am, Monday 16 June until early July.
    • Local access maintained.

Albert Street

  • Closed between McDonald Street and Ashmore Avenue from 7am to 5pm, Thursday 5 June.
  • Closed between Lewis Street and Bear Street from 7am to 5pm, Sunday 22 June.
    • Access to and from Bear Street and McDonald Street via traffic management only.
  • Road closed between Lewis Street and McDonald Street from Wednesday 25 June to Sunday 6 July, with local access maintained.

Mordialloc Stabling Yard underpass

  • Underpass closed from Monday 9 June to 11.59pm, Monday 29 June. Updated Monday 23 June
    • Please follow local detour signage.

Mordialloc Creek boat access

  • Closed from the Governor Road boat ramp to west of the Mordialloc Creek rail bridge from 7am to 5pm, for 3 non-consecutive days in late May and June.
    • Please see signage at boat ramp for details.

Main Street Service Road (south of McDonald Street)

  • Access from McDonald Street closed from Monday 16 June to early July.
    • Alternative entries for Main Street/Nepean Highway entries.
  • Approximately 15 car spaces closed from Monday 16 June to early July.

Nepean Highway

  • Intermittent lane and parking closures between Station Street and Kara Grove, under traffic management throughout June.

Station Street

  • Vehicles detoured onto temporary road between the level crossing and Attenborough Road Thursday 3 July to early August.

Attenborough Road

  • Road closed at the intersection with Station Street from Thursday 3 July to early August.
  • Detour via Pine Crescent.

Bus

  • Changes to PTV bus stops on Albert Street until late 2026.
  • View information about ongoing changes to local bus routes and bus stops on the PTV website.
  • SkyBus services will not stop at Mordialloc until early 2026. Alternative stops are located at Mentone and Chelsea.
  • For information about SkyBus routes, visit the Skybus website. You can also contact Skybus directly by calling 1300 759 278 or emailing info@skybus.com.au.

Pedestrian

Mordialloc Creek Reserve (Attenborough Park)

  • Pedestrian paths closed near the Station Street level crossing and throughout the Reserve from Monday 26 May to Friday 16 June.
  • Detours in place via Bear Street and southern creek underpass.
  • Please allow extra time and follow detour signage.

Car parking

Pine Crescent and Pine Court

  • Sections of street parking closed to make room for temporary no-standing zones to enable safe traffic movements during road closures from Thursday 21 July until early August.

Mordialloc Station car parks

  • Changes to commuter parking and access until late 2026.
    • Visit the PTV website for more information and alternative parking locations
    • Please check signage at the station as works continue.