30 April 2025

We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale by building new rail bridges. We’re also removing and closing the Bear Street level crossing in Mordialloc and building a new Mordialloc Station.

What we’re doing

During May, we will:

  • complete earthworks and piling in the rail corridor on Albert Street, Mordialloc between McDonald and Bear streets, as well as on Station Street, Aspendale between Attenborough Road and Ruvina Street
  • construct hardstand in the rail corridor near Pine Crescent, Aspendale to support heavy machinery
  • install new rail services in Mordialloc and Aspendale
  • continue vegetation removal and install safety fencing along the rail corridor
  • temporarily relocate the Mordialloc Station bus interchange from the station (west) side of Albert Street to the other side of the road to make room for ongoing works near the station.

Utility companies will continue relocating services (electricity, gas and water) to make way for construction works. Temporary service interruptions to private properties may occur, and your utility provider will notify you ahead of time.


Mordialloc Creek and the Governor Road boat ramp temporary closures

Public access to Mordialloc Creek will be closed from the Governor Road boat ramp to west of the Mordialloc Creek rail bridge over 3 non-consecutive days in May and June while we bore under the creek to install underground rail services.

We’ll install signage at the boat ramp ahead of closure dates and notify community groups and any affected mooring holders in advance. These works will not affect access to the nearby pedestrian bridge or paths.


What to expect

Throughout May, you should expect changes to road conditions, parking, and pedestrian paths. You may notice an increase in construction workers and machinery, including moderate noise and vibration at times. Please expect delays on Nepean Highway in both directions, predominantly southbound, and allow extra travel time.

We’ll work 7am to 6pm on weekdays and 7am to 3pm on Saturdays. We’ll also work 24/7 from 8.30pm Friday 16 May to last service Sunday 18 May in the rail corridor. If we need to work outside of these times, we’ll let the community know in advance.


Changes to the way you travel in Mordialloc

McDonald Street

  • Closed between Albert Street and Main Street Service Road from:
    • 8pm, Thursday 8 May to 5am, Friday 9 May
    • Saturday 24 May and Sunday 25 May, 7am to 4pm each day.

United Energy will notify residents ahead of time.

  • Closed between Albert Street and Main Street Service Road for 3 weeks from June – dates will be notified closer to the time.
  • Pedestrian detour routes remain in place until late 2026.

Mordialloc Creek

  • Closed from the Governor Road boat ramp to west of the Mordialloc Creek rail bridge from 7am to 5pm for three non-consecutive days in May and June. Please see signage at boat ramp.

Changes to the way you travel in Aspendale

Station Street

  • Intermittent lane closures under traffic management until late 2026.

Mordialloc Creek carpark

  • Closed until late 2026. Three car parking spaces to remain open for access to boats.

Upcoming travel changes for public transport

Frankston and Stony Point lines

  • Buses will replace trains between Cheltenham, Frankston and Stony Point stations from 8.30pm, Friday 16 May to last service, Sunday 18 May.

Mordialloc Station car parks

  • Changes to commuter parking and access at times until late 2026. Visit the PTV website for more information.

Bus routes

  • View information about ongoing changes to local bus routes and bus stops at the PTV website.

For the safety of the community and our workers, traffic management will be in place throughout the area with short stops to pedestrians and vehicles at times while machinery and trucks are moving through the area.