24 April 2024
The Victorian Government is removing 27 dangerous level crossings and building 17 new stations, making the Frankston Line level crossing free by 2029 and improving safety, reducing congestion, and allowing more trains to run more often. We’re removing the level crossings at Warrigal Road, Mentone and Parkers Road, Parkdale, and building a new Parkdale Station.
What we’re doing
During May, we will continue to deliver and install concrete beams for the new rail bridge.
We will also:
- begin construction on the rail track and overhead structures that make up the rail bridge
- deliver and install station precinct buildings
- continue drainage and utility works during the day along Como Parade East, Como Parade West and Peter Avenue
- continue to build the retaining walls and abutments at the northern and southern ends of the project
Works will take place during the following times in sections of the rail corridor:
- 7am to 6pm weekdays
- 7am to 3pm Saturdays
- 7pm to 7am nightworks
During June, we will also work 24-hours between 14 to 17 June and 21 to 24 June. More information about these works will be provided in our June notification.
What to expect
- Increased activity overnight as trucks and cranes deliver and install concrete structures
- Moderate to high noise and vibration from machinery, including cranes, excavators and trucks
- Minor delays and detours on roads and footpaths, and lane closures
- Minor traffic delays near site access gates for increased truck and trailer movements and deliveries
- Additional truck movements and vehicles for support crews
- Temporary lighting in place to safely illuminate work areas during night shifts
- The carpark on the corner of Como Parade East and Parkers Road will close from early May until early August
During June, we will also work 24-hours between 14 to 17 June and 21 to 24 June. More information about these works will be provided in our June notification.
Changes to the way you travel – road and pedestrians
- The Warrigal Road and Parkers Road road and pedestrian crossings will close intermittently in May and June. Check local signage and SMS updates for detour options
- Como Parade West will remain closed southbound, from Parkers Road to Royal Parade until early August
- Como Parade West will close in sections from 9pm to 7am in May for delivery of bridge beams with detours clearly signed and access to properties maintained
- Como Parade West will remain closed between McIndoe Parade and Dalmor Street until early June
- Como Parade East will remain closed northbound from Parkers Road to Barry Street until project completion
- Peter Avenue will be single-lane operational with parking and footpath impacts from mid-May until early June
- Affected residents will be contacted in advance
Pedestrian crossing access is likely to change frequently, we strongly suggest checking the Big Build website before leaving home.
Changes to the way you travel – train
- 8:30pm Friday 14 June to last service Sunday 16 June
- 8:30pm to last service each night, Monday 17 June to Thursday 20 June
- 8:30pm Friday 21 June to last service Sunday 23 June
Buses replace trains between Caulfield and Mordialloc from:
Buses replace trains between Moorabbin and Frankston from:
Signage will direct passengers to replacement bus stops.
For up-to-date information on service changes, please visit the PTV website, or call 1800 800 007.
Works area map
More information
This notification provides an overview of works planned for May however, details may change. Please be aware that works sometimes take longer than expected or need to be rescheduled due to weather and other factors outside our control.
If you have any questions or would like more information about the project, call us on 1800 105 105, 24/7.
- Subscribe to SMS updates by texting PARKDALE to 0429 839 892
- Sign up for email updates
- Visit our social media channels
- For languages other than English, please call 03 9209 0147.