10 July 2025
We’re removing 4 dangerous and congested level crossings at Coburns, Exford and Ferris roads in Melton, and Hopkins Road in Truganina to make Melton boom gate free in 2026. We’re also building a new modern and accessible Melton Station.
What we’re doing
To construct the foundations for the new rail bridge over Exford Road, we’ll be undertaking works on Creek Street at times from Tuesday 22 July until January 2026.
These works include relocating the underground water main, installing construction foundations and building the supports for the Exford Road rail bridge.
Drainage works in July and August
From Tuesday 22 July to Friday 8 August, we’ll be relocating the underground water main on the southern side of Creek Street.
These works will be completed from 7am to 6pm, Monday to Friday and from 7am to 1pm on Saturdays.
We’ll start works at the western end of Creek Street near Exford Road and move east as works are completed at each location. A section of the west bound lane on Creek Street will be closed during these works.
We’ll need to close access to the eastern end of Creek Street as we trench across the road for one day during these works from 9am to 3.30pm.
We’ll confirm this date ahead of any potential impacts and we’ll work with residents to manage property access requirements.
Changes to the way you travel
Road
- Vehicle access to residential driveways on Creek Street will be temporarily unavailable for up to 3 hours at a time.
- Pedestrian access will be maintained.
- Driveway access can be maintained for emergency access.
Parking
- On-street parking removed on the southern side of Creek Street during works.
What to expect
- Construction vehicles and workers in the area.
- An increase in noise and traffic movements in the area.
Please allow extra time when travelling through the area.
We’ll make every effort to complete works on schedule; however dates are subject to change.
Works area map
Creek Street watermain works

Creek Street trenching works

More information
- Text MELTON to 0428 581 917 to sign up for SMS text updates about Melton Station.
- Text FERRIS to 0439 979 482 to sign up for SMS text updates about Ferris Road level crossing removal.
- Text HOPKINS to 0438 702 491 to sign up for SMS text updates about Hopkins Road level crossing removal.
- Visit our website for more information about the Melton level crossing removals
- Send us a private message on the Level Crossing Removal Project Facebook page
- Contact our call centre on 1800 105 105 or email us at contact@levelcrossings.vic.gov.au