29 March 2025
We’re removing 4 dangerous and congested level crossings at Coburns, Exford and Ferris roads in Melton, and Hopkins Road in Truganina to make Melton boom gate free in 2026. We’re also building a new modern and accessible Melton Station.
We’re removing the level crossing at Hopkins Road by building a new road bridge over the rail line. Works to construct the foundations of the road bridge are underway with piling almost complete.
What we’re doing
- Continuing earthworks to construct the base of the new road bridge.
- Completing piling on both sides of the rail corridor.
- Removing redundant infrastructure along Hopkins Road.
- Transporting large vehicles and machinery across the construction site and via Hopkins Road.
- Pouring concrete to form the road bridge foundations and walls.
Night works in April
- The project will complete survey works in the rail corridor between 10pm and 4am from Friday 11 April to Sunday 13 April, while no trains are running.
- Impacted residents and stakeholders will be notified directly, however we expect these works to be low impact with handheld equipment only.
What to expect
- Increased construction personnel, vehicles and equipment in the area.
- Increased noise, dust and vibration.
- Traffic management, including lane closures and reduced speed limits at times. Minor delays may be experienced.
- General working hours are Monday to Friday, 7am to 6pm and Saturday from 7am to 3pm.
More information
- Text MELTON to 0428 581 917 to sign up for SMS text updates about Melton Station.
- Text FERRIS to 0439 979 482 to sign up for SMS text updates about Ferris Road level crossing removal.
- Text HOPKINS to 0438 702 491 to sign up for SMS text updates about Hopkins Road level crossing removal.
- Visit our website for more information about the Melton level crossing removals
- Send us a private message on the Level Crossing Removal Project Facebook page
- Contact our call centre on 1800 105 105 or email us at contact@levelcrossings.vic.gov.au