16 November 2026
We’re removing the Ruthven Street, Macleod level crossing by building a rail bridge over the road. Construction to build the new rail bridge is underway.
We’ll work during the day and overnight along the rail corridor from Invermay Grove, Rosanna to Powley Parade, Watsonia and at Macleod College oval in December.
There will be no construction from Friday 18 December to Tuesday 12 January 2027.
What we’re doing
- Installing underground services and cabling, signalling, maintenance pits, and foundations to support new rail lighting and electrical infrastructure.
- Delivering rail track in the rail corridor between Invermay Grove, Rosanna and Powley Parade, Watsonia at night.
- Continuing upgrade works at Macleod College oval, including installing new drainage and irrigation systems, lighting and the new multi-use classroom with bathrooms and change room facilities.
- Installing new kerbing on Powley Parade to support formalising the road rail access pad. These works were rescheduled from November.
What to expect
- Construction during the day and at night. Most works will take place from 7am to 6pm, Monday to Friday and 7am to 1pm, Saturdays. Overnight works include:
- rail deliveries with increased noise from 9pm to 5am each night, Wednesday 2 December to Thursday 3 December
- overhead wiring and utility works on Ruthven Street near the level crossing from midnight to 5am, Tuesday 15 December and Wednesday 16 December.
- Changed traffic conditions with traffic management in the area, with temporary lane and walking and cycling path closures on Chapman Street, Ellesmere Parade south of the Davies Street pedestrian level crossing, and McNamara Street.
- Increased construction vehicles on local streets including Somers and Melrose avenues while we upgrade the Macleod College oval.
- Increased noise, dust and lighting. Water carts will be used to mitigate dust.
- Temporary closures of car parks at Macleod Station.
We’ll make every effort to complete works on schedule; however, dates and times are subject to change.
Directly impacted residents will be notified in advance.
Changes to the way you travel
Hurstbridge Line
- Buses replace trains between Heidelberg and Greensborough from 8.30pm to last service each night, Wednesday 2 December to Thursday 3 December.
Chapman Street, Macleod
- Temporary footpath closures and lane narrowing in mid December.
Melrose and Somers avenues, Macleod
- Macleod College oval closed to the community and traffic management on Melrose and Somers avenues until early 2027.
More information
- To sign up for SMS updates about changes to the way you travel through the area text RUTHVEN to 0428 581 917..
- For more information about the project, call us on 1800 105 105 or email us at levelcrossings@bigbuild.vic.gov.au 24/7.
- For languages other than English please call 9209 0147.