2 September 2024
The Lilydale Line is level crossing free - a year ahead of schedule.
The dangerous and congested level crossing and roundabout in Croydon has been removed by elevating the rail line, with trains now running along the new rail bridge and cars traveling along the new Kent Avenue to Lacey Street road connection.
The new Croydon Station is now open. We will continue working until spring on the transport hub, car parks, and landscaping.
Works taking place during September 2024
Road
Pierson Drive
- Closed between Main Street and Railway Grove as road works continue. Access maintained maintained to Croydon Station, DDA parking and MTM staff parking.
Railway Crescent and Croydon Road
- Access to and from Railway Crescent at stages will take place from Tuesday 3 September and throughout Spring which may include temporary driveway closures and pedestrian access. We’ll be in touch with individual properties to discuss any impacts. Access into and out of Railway Crescent will be maintained via Kitchener Road. Traffic management will be in place to direct pedestrians and vehicles.
Eastern car park area and Coolstore Road
- Throughout Spring drainage works will commence within the site adjacent to Railway Crescent and Coolstore Road in preparation for the new station car park.
- Drainage works will commence in Coolstore Road near the rail corridor in September 2024. Further detail will be provided to impacted businesses.
Kent Avenue/Croydon Road and Lacey Street
- Footpath reinstatement, line marking and light pole installation will take place until the end of September.
- Some footpath and lane closures will be required while these works are undertaken. Please follow the direction of traffic management and signage.
Wicklow Avenue
- Traffic management will be required on Wicklow Avenue at times to facilitate access to and from site. Lane closures can be expected at times.
- The pedestrian footpath on Wicklow Avenue adjacent to Platter Pantry will temporarily close while reinstatement works are carried out day and night from 7am, Sunday 22 September until 5pm, Thursday 26 September.
- The small vehicle access to Croydon Central will also need to temporarily close during this period. The main entrance on Wicklow Avenue will remain open. Please follow the direction of signage.
Toorak Avenue
- Lane closures at Wicklow Avenue from 7am, Sunday 22 September until 5pm, Thursday 26 September.
- Shuttle flow will be in place. Please follow the direction of traffic management and signage.
Croydon transport hub and bus interchange
- Throughout Spring, night works may be required between 7pm and 7am on weekdays and may also take place day and night on Saturdays and Sundays to complete the new Croydon transport hub and interchange.
- The Devon Street site compound and laydown areas will be used during this period.
Northern car park area
- Night works will continue between 7pm and 7am each night until late August to keep building the new Croydon Station and Transport Hub, including installing station services, delivering station buildings, steel fixing and concrete pours.
- These works will also take place on Saturdays and Sundays from 7am to 6pm. The Devon Street site compound and laydown areas will be used during this period.
Devon Street
- Drainage works are expected to commence mid-October. We will provide a detailed works alert and speak with individual stakeholders prior to works starting.
Railway Grove
- Will be closed while we build the retention basin from mid-October until mid-November.
Railway Crescent wayfinder map
What to expect
- There will be changes to the way you travel around the area while we work. Please take care when moving around the works areas and pay attention to pedestrian detour signage in place.
- Traffic management will be in place to assist vehicles and pedestrians around works areas throughout these works. Some minor delays may be expected at times whilst heavy machinery and vehicle movements take place.
- These works may include delivery of materials, plant and machinery, utility relocations, road asphalting, reinstatement and other work activities. We will provide detail of these works to impacted residents and businesses.
- You may experience moderate noise from machinery such as piling rigs, cranes, rollers, and excavators.
- Please be aware works can sometimes take longer than expected or need to be rescheduled due to weather and other factors outside of our control.
Thank you for your patience
Thank you for your patience during these works. We understand that our works are disruptive and we remain available to discuss your needs.
If you have any questions or would like to discuss additional support options that may be available for you, please contact us.
Stay up to date
- Call us on 1800 105 105 24/7
- Subscribe to email updates
- Visit our Level Crossings Facebook Page
- View all current disruptions