21 December 2022
We're building the rail bridge over McGregor Road, Main Street and Racecourse Road and delivering new stations at Pakenham and East Pakenham.
Works are progressing at Pakenham as we build the elevated rail bridge. At times, we will need to close McGregor Road, Main Street and Racecourse Road at the level crossings. While these works take place, traffic management will help people move around the area.
We will provide regular updates ahead of works as well as the latest project information and timelines.
How we’ll work with you
Understanding your business and working with you is important to us.
Our commitment to you and your business is to:
- have dedicated staff to keep you up to date about the project and timing of impacts
- ensure you have information about detours or changes to access to help your staff and customers get around
- conduct marketing campaigns to encourage the community to continue to shop locally during works
- procure goods and services locally, where we can
- manage traffic and workforce parking to minimise the impact to local roads.
Traffic impacts 2023
Dates | Road | Duration (approximate) | Activity |
---|---|---|---|
Wednesday 11 January to Saturday 14 January | Racecourse Road | 3 Days | Piling works |
Mid February 2023 | McGregor Road | 2 Days | Installation of rail bridges beside road |
Tuesday 21 February to Friday 10 March | Main Street | Approx.3 weeks | Piling works on Main Street, pier construction and road works |
Early 2023 | McGregor Road | 7 Days total | Installation of rail bridge structure over road |
Mid 2023 | McGregor Road | 3 Days | Installing screening on rail bridge |
Mid 2023 | Main Street | Approx. 1 Week | Installation of rail bridge structure over road and screening |
Get in touch
- Text Pakenham to 0428 581 917 to sign up for text messages about road disruptions.
- Sign up to regular project updates select Pakenham Level Crossing Removal Project.
- If you have any questions, concerns or would like to organise a face-to-face meeting about upcoming project works, call us on 1800 105 105 or email contact@levelcrossings.vic.gov.au