24 September 2026
Longer 9-car VLocity trains will be able to run on the Melton Line next year, one year ahead of schedule.
To house the new trains we’re building a new train stabling yard in Cobblebank, 700m east of the new Melton Station.
Running longer trains will boost passenger capacity by 50% during peak services.
The new Cobblebank stabling yard will enable trains to be at Melton Station for first services each day, improving reliability, increasing capacity on the line and supporting future growth in Melbourne’s west.
To allow the longer trains to stop at some of the busiest stations on the line, we’ve extended the platforms at Cobblebank, Rockbank, Caroline Springs and Deer Park stations.
Nine-car VLocity trains running from Wyndham Vale will start servicing Deer Park Station this spring.
Project benefits
- Longer 9-car VLocity trains will be able to run on the Melton Line from 2027
- Increasing passenger capacity by 50%
- Nine-car VLocity trains servicing Melton, Cobblebank, Rockbank, Caroline Springs, Deer Park and Southern Cross stations
- Future proofed to stable Metro trains when the Melton Line is electrified
- New Victorian-built VLocity fleet
About the Cobblebank train stabling yard
Trains will be stored, cleaned and prepared for service in the yard.
The stabling yard will operate 24/7.
The location along Abey Road provides network efficiencies due to its proximity to Melton Station and reduces the need for new train tracks and other disruptive works.
The stabling yard will be future proofed to stable Metro trains when the Melton Line is electrified.
Once the Melton Line is electrified, the new yard will enable Metro trains to be at Melton Station, ready for first services to the CBD.
Key features of the yard
- Energy and water efficient air conditioning units and appliances
- CCTV and directional lighting to minimise light spill
- Landscaping around perimeter of 300 native trees and 20,000 native shrubs, grasses and groundcovers to screen the yard and to provide additional security
- Stabling for 6 9-car VLocity trains and future proofed for Metro trains Leggatt St Vehicle access off Abey Road and parking for workers and train drivers
- Water retention basin that collects, stores and treats stormwater from the yard
- Use of sustainable concrete mixes, recycled plastic aggregates and reclaimed timber furniture
- Vehicle access off Abey Road and parking for workers and train drivers
- A 46 kilowatt solar system made up of 110 solar panels Clowe Ballarat Rail corridor
- Signalling and communication systems, including a train radio tower
Building the stabling yard step by step
- Setting up the site
- Early works began with establishing the site and demolishing and removing existing buildings.
- Installing underground service
- Before construction above ground begins, we're installing essential underground services across the site such as drainage, sewerage, electrical and signalling cables.
- Constructing the tracks
- We're building the stabling tracks in layers, starting with preparing the ground and creating a stable foundation before placing ballast and laying sleepers and tracks. Southern Cross
- Connecting to the Melton Line
- The stabling yard tracks are connected to the existing Melton Line and the yard will be future proofed for electrification of the Melton Line.
- Installing signalling systems
- We're installing signals, trackside equipment and control systems that support safe and reliable rail operations.
- Access and facilities
- We're building new facilities to support the operations of the stabling yard including staff amenities, equipment rooms and storage areas. We're also building internal access roads, a 40-space staff car park and a new left turn slip lane from Abey Road into the stabling yard.
- Landscaping
- We'll landscape around the perimeter with 300 native trees and 20,000 native shrubs, grasses and groundcovers to screen the yard and to provide additional security.
- Completion
- Once construction and testing are complete, new 9-car VLocity trains will arrive at the Cobblebank stabling yard.
Melton electrification works
The Australian and Victorian governments have jointly funded $152.7 million to kick off development work for the Melton Line electrification.
Site investigation works started in July and will continue along the rail corridor to inform the timing, design, scope and cost for future delivery of the project.
Electrification will allow more trains to run along the Melton Line, servicing the booming communities in Melbourne’s west.
Sustainability initiatives
Landscaping and biodiversity
Around 300 native trees, including Yellow Box, Mugga Ironbark and Brittle Gum, will be planted alongside 20,000 native shrubs, grasses and groundcovers.
An existing dam next to the site and its surrounding area is being retained and will not be disturbed during construction and future stabling yard operations.
The project will monitor the area for 2 years to ensure that all vegetation is properly maintained. After that, care of the maturing green space will be transferred to the appropriate authority.
Waste reduction
Recycled plastic and low carbon concrete mixes will be incorporated in concrete slabs and footpaths.
Furniture in staff facilities will include timber repurposed from trees removed during construction.
We're installing low carbon rail sleepers and we'll reuse rail materials from the Melton level crossing removal project.
Energy efficient and low emissions design
A 46-kilowatt solar power system made up of 110 solar panels will be installed, along with energy and water efficient air conditioning units and appliances helping reduce reliance on grid electricity and lower operational emissions