9 May 2024
The Werribee Street and Cherry Street level crossings are gone for good, making central Werribee completely level crossing free.
In May, we'll work to replace some areas of damaged kerb along Princes Highway.
What we're doing
We’ll work near the corner of Tarneit Road and Princess Highway, on the eastbound lanes to remove and replace some sections of kerb in the median.
During this time, we’ll:
- work overnight from 9pm to 5am, Monday 20 May and Tuesday 21 May
- have a small working crew in the area and traffic management in place
- ensure that two-way traffic will be maintained at all times.
What to expect
You may notice truck movements, noise, dust and vibration during these works. When we work at night, additional lighting will be in place and will be directed away from residential properties where possible.
Changes to the way you travel
Princes Highway, near corner of Princes Highway and Tarneit Road
- Closure of an east-bound fast lane from 9pm to 5am, Monday 20 May and Tuesday 21 May.
- Two-way traffic will be maintained at all times.
More information
Call us on 1800 105 105 or email contact@levelcrossings.vic.gov.au