20 February 2025
Bulleen Park Sports Upgrade is part of North East Link’s more than $100 million sports and recreation program to deliver game-changing community benefits that will keep local clubs playing and thriving during construction and beyond.
We’re almost ready to start upgrading Bulleen Park with contract awarded in late January 2025. The project team is now preparing for early works on site. Significant progress has also been made on the design of the upgrades, with workshops held in December 2024 with key stakeholders.
When we'll be working
- Monday to Friday 7am to 5pm
Temporary car park
From early March, we’ll start building the temporary car park at the western end of the park to enable visitors to use the park during construction.
The car park will be open from mid-April with 151 spaces before we gradually start closing the existing car spaces for upgrade works.
Access to Bulleen Park
Public access and parking at Bulleen Park will be maintained.
Access to the temporary car park will be from the current access route via Bulleen Road.
The existing pedestrian path north of the site adjacent to the Yarra River will remain unaffected. As upgrade works progress, we’ll set up temporary fences and pathways with clear signage to guide you through the area.
Site set-up from early 2025 (indicative)
Environmental and safety measures
We carefully manage our works in line with the project’s strict environmental performance requirements including:
- monitoring noise and dust levels to ensure compliance with regulations
- speed restrictions for vehicles
- implementing regular water cart spraying and environmental controls
- using traffic management to safely guide drivers, cyclists and pedestrians through the area.
For the safety of the public and our workers, only authorised personnel are permitted in work areas.
For languages other than English please call 9209 0147.
Please contact us if you would like this information in an accessible format. If you need assistance due to a hearing or speech impairment, visit relayservice.gov.au