9 May 2025
Works are progressing across all of our sites with foundations for structures and bridges beginning to form on the freeway shoulders and centre median.
Construction snapshot
Over 100 Super T beams have been installed to support a newly aligned Bulleen Road. Crews will now focus on completing the top deck of Bulleen Road in readiness for opening to traffic later this year.
Across Bulleen, Balwyn North, Doncaster, and Mont Albert North we'll continue piling, earthworks, drainage installation, utility relocations, asphalting, site investigations and barrier realignments to widen the freeway, and build new ramps and bridges.
We're here to help
We understand that construction in the local area can be challenging. Call 1800 105 105 anytime or visit the Project Information Centre at 284 Doncaster Rd, Balwyn North, Tuesday to Thursday, 9am to 3pm.
When are we working
Day works 7am to 6pm from Monday to Friday and 7am to 3pm Saturdays and Sundays
Night works 7pm to 6am from Monday to Saturday
24-hour works (at times)
Notification provided before works
Schedule is subject to change. Visit bigbuild.vic.gov.au/roads for changes. Please contact us if you would like this information in an accessible format. If you need assistance due to a hearing or speech impairment, visit relayservice.gov.au
Zone 1: Burke to Bulleen roads, Eastern Freeway interchange
Ongoing/existing works
Zone 2: Bulleen Road to Doncaster Road, Koonung Creek Reserve
Ongoing/existing works
Zone 3: Doncaster to Tram roads, Valda Wetlands
Ongoing / existing works
For more information call 1800 105 105 or visit the Project Information Centre at 284 Doncaster Road, Balwyn North.
For languages other than English please call 9209 0147.