14 July 2026
We’re completing the M80 Ring Road, delivering new lanes from Plenty Road to Watsonia, including a seamless connection to the North East Link tunnels, taking up to 15,000 trucks off local roads a day.
What you need to know
Major work is continuing on Grimshaw Street from July through to mid 2027, as we build an upgraded Grimshaw Street Interchange.
During this time, we’ll also complete essential utility and finishing works on the west side of the Grimshaw Street interchange. Grimshaw Street will be closed between Macorna Street and the Greensborough Bypass over a weekend, with detours in place to keep motorists and pedestrians moving safely.
In July, Grimshaw Street will be closed temporarily between Macorna Street and the Greensborough Bypass for one weekend as we complete essential utility and finishing works to complete the west side of the Grimshaw Street Interchange. Local access will be maintained.
In August, we'll close Grimshaw Street overnight on a weekend between the Greensborough Bypass and William Street to install signage gantries.
In September, the way you travel through the Greensborough Bypass, Greensborough Highway and Grimshaw Street intersection will change.
Temporary signalised U-turns will be introduced to maintain traffic flow while crews excavate the new express lanes for the North East Link tunnels and build the new Grimshaw Street bridge. This travel arrangement will be in place until mid 2027.
To prepare, there will be a weekend closure across key approaches to the intersection. Grimshaw Street intersection will be closed between Fyre Street and the Greensborough Bypass, and between Greensborough Road and the Greensborough Bypass for one weekend as we continue upgrading Grimshaw Street.
Grimshaw Street Interchange, Greensborough – west side closure
Grimshaw Street closed in both directions between Macorna Street and Greensborough Bypass from 9pm, Friday 24 July to 5am, Monday 27 July.
- Detour via Grimshaw Street, Plenty Road, M80 Ring Road and Greensborough Bypass.
- Delays of up to 20 minutes.
Bus routes 566 and 902 detours
Bus Route 902 will operate via the M80 Ring Road between Greensborough Station and Keon Park Station, skipping all stops on Settlement Road, Plenty Road, and Grimshaw Street from 9pm, Friday 24 July to 5am, Monday 27 July.
Bus Route 566 will not service bus stops along Sellers Street, Gillingham Street, and Grimshaw Street from Macorna Street to Greensborough Bypass from 9pm, Friday 24 July to 5am, Monday 27 July.
- Shuttle buses will run every 30 minutes between Greensborough Station and Keon Park Station.
- The shuttle bus will not service bus stops along Sellars Street, Gillingham Street, and Grimshaw Street from Macorna Street to Greensborough Bypass.
- Customers will need to walk to the nearest stop on Macorna Street or Grimshaw Street.
Grimshaw Street Interchange, Greensborough - east and west side closure
Grimshaw Street closed in both directions between Frye Street and Greensborough Bypass and between the Greensborough Bypass and Greensborough Road from 9pm Friday 11 September to 5am, Monday 14 September.
- Detour via the Greensborough Bypass, M80 Ring Road, Plenty Road and Grimshaw Street, and via Grimshaw Street, The Circuit, Diamond Creek Roundabout and Greensborough Bypass.
- Delays of up to 30 minutes.
Bus routes 566 and 902 detours
Bus Route 902 will operate via the M80 Ring Road between Greensborough Station and Keon Park Station, skipping all stops on Settlement Road, Plenty Road, and Grimshaw Street from 9pm Friday 11 September to 5am, Monday 14 September.
Bus Route 566 will not service Grimshaw Street between Frye Street and Greensborough Plaza from 9pm Friday 11 September to 5am, Monday 14 September.
- Shuttle buses will run every 30 minutes between Greensborough Station and Keon Park Station.
- The shuttle bus will not service bus stops along Grimshaw Street between the Greensborough Bypass and Henry Street.
- Customers will need to walk to the nearest stop at the undercover bus interchange opposite Greensborough Station.
When we’ll be working
We'll carry out most of our works during the day, although some night works will be required.
When we’re required to work at night near homes and businesses, we’ll provide advance notice.
Managing construction impacts
We manage our works responsibly in line with strict project requirements including:
- keeping residents and businesses informed when work is happening nearby
- using clear signage and traffic controls to safely guide drivers, cyclists and pedestrians
- securing worksites with fencing, barriers and safety measures
- monitoring and managing noise, dust, and vibration levels in real time
- minimising light spill with carefully directed lighting
- implementing environmental controls to prevent dust and water run-off
- containing workforce parking within designated worksites.
What to expect
What to expect while we are working:
- machinery, equipment and vehicle noise, light, dust and occasional vibration at times
- ies to worksites, including outside of standard work hours
- light and heavy vehicle movements on local streets, and lane, ramp and road closures.
Keeping in touch
We’ll be out talking to nearby residents and businesses about these works, including how we’ll be managing any local impacts. If you have any questions, please contact the Big Build contact centre on 1800 105 105.
Sign up for SMS and email notifications. By subscribing, you will receive important, location-specific information as it happens.
Schedule is subject to change. Visit our Disruptions for changes. If you have any questions, please contact us on 1800 105 105.