28 February 2021 to 31 December 2022
Notification - installation of noise walls
The West Gate Tunnel Project team will soon begin installing new, high-quality permanent noise walls in your area.
The new noise wall will be between eight and nine metres high and will be made of textured concrete panels with pale blue and green coloured acrylic panels at the top in some sections.
As well as being more attractive, the new noise walls will provide you much better protection from freeway noise than the old noise walls.
They have been designed to achieve a daytime average noise level of 63dB(A) at nearby houses, which will mean a significant reduction in noise levels for many residents. Where space permits, planting will also be used to screen the noise walls.
When we expect to start installing noise panels in this area: starting from mid-March, installation of panels will take approximately eight weeks · acrylic panels (needed in some locations) will be installed mid-to-late 2020 · existing noise wall will be removed once the new panels have been installed
Notification - installation of noise walls
The West Gate Tunnel Project team will soon begin installing new, high-quality permanent noise walls in your area.
The new noise wall will be between eight and nine metres high and will be made of textured concrete panels with pale blue and green coloured acrylic panels at the top in some sections.
As well as being more attractive, the new noise walls will provide you much better protection from freeway noise than the old noise walls.
They have been designed to achieve a daytime average noise level of 63dB(A) at nearby houses, which will mean a significant reduction in noise levels for many residents. Where space permits, planting will also be used to screen the noise walls.
When we expect to start installing noise panels in this area: starting from mid-March, installation of panels will take approximately eight weeks · acrylic panels (needed in some locations) will be installed mid-to-late 2020 · existing noise wall will be removed once the new panels have been installed
During this time
- Driveway and footpath access to residential properties along Fogarty Avenue will be maintained.
- Street parking along Fogarty Avenue, from Wembley Avenue to The Boulevard, will be unavailable while the works take place.
What to expect during these works
- Construction vehicles including concrete trucks, pumps and cranes will be moving in and out of the work areas
- Dust and dirt will be minimised by using water spray trucks, street sweepers and covering dirt and rock when it’s transported
- Main access to the construction site will be via West Gate Freeway with minimal site access required via local roads
- Traffic changes including lane and road closures will be required.
For latest updates, dates of closures and detour route information please visit the Victoria's Big Build Disruptions webpage.
Please note that works are subject to change and may be rescheduled in the event of unexpected impacts to the construction program. Thank you for your patience during these works.