11 July 2022 to 31 December 2022
Building the new bridges over the Maribyrnong River
We are starting to build the new bridges over Maribyrnong River. These bridges will support the main carriageway and the entry and exit ramps from MacKenzie Road to the West Gate Tunnel.
What to expect and when
As part of construction of the new bridges, there will be intermittent full closures of the Maribyrnong River south of Shepherd Bridge during the day. These closures are required in order to construct the bridges ensuring the safety of river users.
Download the notification to view a map of the affected area.
| Impact | Date |
|---|---|
| Full river closure. The river will not be accessible throughout periods of this closure. | 25 July to 30 September, 7am to 5pm |
If the weather is poor, or there are any unexpected events, we may need to reschedule these works.
Thank you
We appreciate our work can be disruptive and thank you for your patience and understanding as we carry out this construction.
Works may be rescheduled in the event of unexpected impacts.