1 April 2022 to 31 December 2022
Building bridge supports for the new shared walking and cycling path
Works will commence on the bridge supports in Railway Place and Miller Street Reserve for the new shared walking and cycling path adjacent to Dynon Road and a new barrier along Dynon Road.
What to expect
On the 11 April 2022, bridge foundation works will be commencing within the park with intermittent day noise anticipated.
If the weather is poor, or there are any unexpected events, we may need to reschedule these works.
Impact | Date |
---|---|
Noisy day time works We expect noise to be at a medium level due to bored piling. |
11 April 2022 – 13 May 2022 Weekdays 7:00am – 5:00pm, some Saturdays 7:00am – 1:00pm No works will be conducted on public holidays or rostered days off (15 – 25 April, 9 May). |
Noisy day time works We expect noise to be at a high level due to driven piling. |
16 May 2022 – 27 May 2022 Weekdays 7:00am – 5:00pm No works will be conducted on rostered days off (23 May). |
Walking and cycling detours | Please download notification for map. Detours will change as works progress. |