12 September 2022 to 31 December 2024
Constructing the southern inbound tunnel entrance near Williamstown Road
We are continuing works at the Inbound Portal near Williamstown Road at the West Gate Freeway. Activities include building the new tunnel portal structure, cross passage excavation and a large temporary crane to lift out the tunnel boring machine.
If any of these works are expected to be particularly disruptive, we will be in touch before they start.
What to expect and when
Impact | Dates |
---|---|
24/7 works associated with gantry crane installation, steel reinforcement works and cross passage construction. |
|
Visual changes as a gantry crane is installed over the TBM retrieval pit. This crane is almost 40m wide and 20.5m tall. | Ongoing |
Construction and large vehicle movements in the area. | Ongoing |
Williamstown Road citybound exit ramp closure 24/7 across several weekends in November. | November 2022 |
Daytime construction noise associated with:
|
September 2022 – January 2023 |
Night-time construction noise |
September 2022 – January 2023 |
Night-time lighting in the portal area Lighting will be angled away from homes whenever possible while working at night | Ongoing |
Southern inbound portal (near Williamstown Road)
Ongoing
Works are continuing to build the portal foundations and tunnel boring machine (TBM) retrieval pit at the citybound entrance to the tunnel. These works include excavation, steel reinforcement and concrete works. Night works will take place between September and October. These works are not expected to be disruptive.
Gantry crane installation
November 2022 (date TBC)
The TBM digging the citybound tunnel is progressing well and ahead of the completion of tunnelling, work will take place to build a temporary gantry crane. The temporary gantry crane will remove the TBM Vida once it is finished its 2.8km journey. The green gantry crane will be built across several weekends in November, with the works to take place 24/7.
The Williamstown Road off ramp at the West Gate Freeway will be closed across the weekends while these works are undertaken.
A reminder will be sent closer to the start of these works. These works are not expected to be disruptive.
Cross passage and smoke duct construction
September – December 2022
The team will build a cross passage and two smoke duct crossings under the cut and cover and retrieval pit at the citybound portal. These are important elements in the tunnel; the cross passage connects the two tunnels for emergency and maintenance while the smoke duct crossings are part of the ventilation system and control the spread of smoke in case of an emergency.
These works will take place 24/7 with daytime works to include mechanical rock excavation and grouting activities. Night works will include low impact noise excavation and stabilisation works, including spraying concrete in the underground excavations. Noise mitigation measures will be implemented during these works and the project team will continuously monitor noise levels.
Residents close to the area will be contacted to discuss these works further if they are expected to be disruptive.
More detail on what you can expect during these works
Water-spray trucks and road sweepers will be used in local streets around our worksites, keeping local roads clean during construction.
Thank you
We appreciate our work can be disruptive and thank you for your understanding. Works may be rescheduled in the event of unexpected impacts.
For updates or questions, please
- call 1800 105 105,
- email us at info@wgta.vic.gov.au,
- visit our website or
- you can drop by our Information Centre at 2 Somerville Road, Yarraville 3013, Monday–Friday 10am–5pm or Saturday 10am–4pm for further information on the project.
Stay updated
Do you live or work near the West Gate Freeway?
Stay informed on the latest works in the area – sign up and be a member of the West Gate Tunnel Project – West Gate Freeway Construction Updates Facebook Group.