31 March 2023 to 31 October 2023
Realigning the Wurundjeri Way intersection between Dudley Street and Collins Street and other works
The West Gate Tunnel Project has already started work on extending Wurundjeri Way over Dudley Street and building an extra lane each way between Dudley and Flinders Streets. Once complete, a new elevated bridge extending Wurundjeri Way over Dudley Street will connect to the new elevated Footscray Road and will link to Dynon Road, creating a CBD bypass that will remove through traffic from the CBD and provide greater connectivity between the north, city and western suburbs.
We need to undertake important works on Wurundjeri Way between Dudley Street and Collins Street to realign the intersection, install new traffic lights, relocate high voltage power cables, construct new drainage and pavement and begin the final foundation works for the new bridge ramps over Dudley Street. This will include the clearing and removal of vegetation in the centre median.
To carry out this work, there will be overnight closures of Wurundjeri Way and 24/7 lane closures.
Access to Marvel Stadium will be maintained. Start times of the closures will avoid events at Marvel Stadium.
Please note, this work may be subject to approvals and permits and may change due to site and weather conditions.
What to expect and when
Detour options are listed on the map overleaf and there will be VMS messaging and on-road signage to guide road users during the closures.
| Impact | Date |
|---|---|
| Night time full closures of Wurundjeri Way between Bourke Street and Dudley Street Local access maintained Please plan ahead and follow detours. | From 31 March until late-April there’ll be full nightly closures in place from 8pm to 5am Sunday through Thursday and; 9pm to 7am Friday and Saturdays Note: these closures will avoid events at Marvel Stadium. |
| Ongoing 24/7 single lane closures northbound and southbound between Dudley Street and Collins Street Please plan ahead and allow extra travel time. | From 3 April lane closures will be in place 24/7 until late October. |
| Speed reduction to 40km/h on Bourke Street approaching Wurundjeri Way Lane reduction to one left and one right turn lane approaching the intersection at Wurundjeri Way. | From 3 April traffic conditions will change on Bourke Street until late October. |
| Occasional noise during the night. We’ll have noise monitors in place to measure and monitor noise. | From 31 March closures will be in place from 8pm to 5am Sunday through Thursday and 9pm to 7am on Friday and Saturdays |
| Construction activity on Wurundjeri Way, truck movements in the area and increased construction activity. | From 31 March to late October 2023 |
| Local access to businesses will be maintained Local businesses in the area remain open and operating during these works. We will continue to engage with businesses that may be directly impacted by our works. | From 31 March to late October 2023 |
Thank you
We appreciate our work can be disruptive and thank you for your understanding. Works may be rescheduled in the event of unexpected impacts.