The first major upgrade of the Eastern Freeway since it was built is taking a big step forward over summer.
Due to the recent hot weather, the changes to the Ringwood-bound freeway lanes between Burke and Bulleen roads has been rescheduled and will now occur from Wednesday 12 February until late March.
Motorists travelling from the city towards Ringwood and Dandenong, are encouraged to use the right lanes as they approach Burke Road to continue on the Eastern Freeway outbound.
Motorists travelling outbound to take the Bulleen Road exit will need to stay in the left lanes after Burke Road. The same number of lanes will be open, however will be split in a 2-by-2-lane configuration. If drivers miss the Bulleen Road exit, they can use the next exit at Doncaster Road to get back on track.
Electronic signs and road markings will be in place to direct motorists, who are asked to drive safely and choose their lane early to avoid making last-minute lane changes.
As part of a massive 6-week program, crews will complete asphalting, mark new lines and carry out profiling works behind barriers to construct new express lanes. Work for new traffic management technology, sewer lines, and drainage will also be carried out.
In March, crews will switch their focus to the other side of the Eastern, splitting the citybound carriageway in 2 to carry out similar works. There will be no changes to ramp access to freeway entry and exit ramps during this split.
Throughout 2025, a massive amount of work will continue to build 45 kms of new lanes and to connect the freeway with the North East Link tunnels.