Getting ready to open - final touches for the West Gate Freeway

Back to Newsfeed

Over the last few months, the West Gate Tunnel crews have made steady progress in finishing off asphalting works around the outbound tunnel exit between Williamstown Road and Millers Road. The crews have also:

  • Completed the cladding on the Southern westbound tunnel exit ventilation structure and other finishing works
  • Completed barrier, kerb, and drainage works around the Williamstown Road westbound entry ramp

To put on the final touches before we open the West Gate Tunnel by end 2025, our crews will now move over to the express lanes between Williamstown Road and Millers Road to complete asphalting and line marking work.

Lane and ramp closures between Williamstown Road and Millers Road

From 11.59pm, Friday 12 September to 10.30pm, Sunday 14 September

  • The West Gate Freeway outbound will be reduced to two lanes 24/7, between Williamstown and Millers Roads
  • Williamstown Road outbound entry ramp to the Freeway will be closed
  • One lane will be closed on the West Gate Freeway inbound between Williamstown and Millers Road on Sunday.

From 10.30pm, Sunday 14 September to 5am, Monday 15 September

  • Overnight closure of West Gate Freeway outbound between Williamstown and Millers Roads.

Motorists are advised that delays of up to 30 minutes are expected and drivers should avoid the West Gate Bridge if they can and seek an alternative route. Visit  the Seasonal Campaign webpage for more information, including detour information.