18 June 2026

We’re upgrading Boronia Station and building a new landscaped plaza on Dorset Road to deliver a modern and accessible precinct for the community.

What we’re doing

Throughout July, we’ll:

  • Continue installing structural steel, external cladding, brick work and roofing on the new buildings.
  • Begin paving the new plaza, station concourse, platform and forecourt areas.
  • Install the concrete foundations of the new platform canopies.
  • Remove the existing footpath through the pocket park and begin installing underground services, light poles and new footpaths.
  • Remove 2 trees on Erica Avenue to enable drainage and pavement works.
  • Begin relocation of the Dorset Road pedestrian crossing and install new kerbs and underground services.
  • Paint and complete minor works around the station precinct and on Erica Avenue.
  • Replace bar fencing and begin painting around the station precinct.

24-hour works in July and August

Crews will work around the clock from Friday 3 to Monday 6 July and Monday 27 July to Tuesday 4 August to:

  • Clean and paint the trench walls around the station platform.
  • Install the roofs on the new platform canopies and the power and lighting for them.
  • Remove the barriers from the edge of the platform, complete paving and install tactile signage.
  • Install ground level screens, replacing the old bar fencing.

During this period, you may notice increased truck movements, noise and vibration during the day and night. We’ll also move vehicles onto the train line at the end of Alfred Street.

Until mid-August we’ll work 24/7 at times around the station precinct. We’ll be in touch with directly impacted residents in advance.

What to expect

You may notice:

  • An increase in noise, dust and vibration near works areas. Our team will have controls in place to monitor and reduce these impacts.
  • Reduced speed limits and traffic management in place around our works.
  • Short intermittent pedestrian and cyclist detours around works areas – please follow signage.

At times we may also need to close a small number of station parking spaces closed for works for short periods of time.

There may be utility works around the station and on Erica Avenue. Utility companies are responsible for notifying the community about any impacts. Please contact your utility provider if you have any questions.


Changes to the way you travel

Additional temporary lane, footpath and road closures may be required at times throughout the works. Please follow signage and detours. Traffic management will be in place during works to safely guide you through the area. We will update directly impacted residents and traders in advance.


Road

Dorset Road, between Chandler and Boronia Road

Sunday 28 June to Wednesday 5 August:

  • Two lanes closed, one northbound and one southbound lane will remain open.

Dorset/Chandler Road intersection

Sunday 28 June to Saturday 4 July, Monday 13 July to Sunday 19 July and Thursday 23 July to Sunday 26 July:

  • Lane closures on Chandler Road, one eastbound and westbound lane will remain open.

Lupton Way

  • Lupton Way closed to vehicles until late September. Detour via Dorset Road.

Erica Avenue

  • Road closures near the corner of Erica and Orchid avenues at times until late 2026.

Car parking

Dorset Road, between Chandler and Boronia Road

Sunday 28 June to Wednesday 5 August:

  • Car parks temporarily closed and reduced footpath width on both sides of the road.
  • Three car parks outside 249 and 253 Dorset Road and three outside 246 and 252 Dorset Road will be permanently closed.

Boronia Station multi-deck carpark

  • Access to the upper level of the multi-deck car park will be closed from Wednesday 1 July to Tuesday 4 August.

Boronia Junction carpark

  • 18 parking spaces next to the station will be closed until late 2026.

Boronia Station car park Genista Avenue

  • Closed until late August.

Boronia Station car park Chandler Road

  • Entry from Chandler Road and most of the car park will be closed from Thursday 2 to Monday 6 July.

Erica Avenue

  • Informal parking closed until late 2026.

Pedestrian

Boronia Station Underpass

  • Closed to pedestrians from Monday 27 July to Tuesday 4 August.

Dorset Road, between Chandler and Boronia Road

Sunday 28 June to Wednesday 5 August:

  • Footpaths closed at times outside of trader hours.

Dorset/Chandler Road intersection

Sunday 28 June to Saturday 4 July, Monday 13 July to Sunday 19 July and Thursday 23 July to Sunday 26 July:

  • Temporary footpath closures (one corner at a time). Pedestrian crossing at Lupton Way.

Lupton Way

  • Pedestrian access between Chandler Road and station entry closed until late September. No access to car parks.
  • Safe pick-up and drop-off zone relocated to the station carpark on Erica Avenue until late September.

Erica Avenue

  • Station-side footpath on Erica Avenue will be closed at times until Tuesday 4 August. Pedestrians can detour around the area on the opposite side of the road.
  • Closed one day in July, footpath detour will be in place.

Corner of Erica Avenue and bus interchange

  • The footpath between the station entry and Erica Avenue will be closed from Monday 1 June to Saturday 20 June. Pedestrians can detour around the area on the opposite side of the road.
  • Footpath at the corner of Erica Avenue and the bus interchange will be closed from Sunday 5 July to Sunday 12 July. Pedestrians can detour around the area on the opposite side of the road. Traffic management in place for vehicles.

Bus interchange

  • Some bus stops have been relocated to the car park north of Chandler Road until late 2026. Pedestrian access via the crossing on Chandler Road. Follow directional signage.

Rail

Belgrave Line

  • Buses replace trains betweenBayswater and Belgrave from 8.30pm Monday 27 July to last service, Monday 3 August.
  • Trains are not stopping at Boronia Station until late spring 2026. A shuttle bus between Bayswater, Boronia, Ferntree Gully stations will connect passengers to train services. The Belgrave Line will remain open for the majority of this time.
  • Buses replace trains at times until spring 2026. Find out more, visit Transport Victoria.

More information