3 March 2026

We’re removing the level crossings at McDonald Street in Mordialloc and Station Street in Aspendale by building new rail bridges. We've already closed the Bear Street, Mordialloc level crossing and are building a new Mordialloc Station.

What we’re doing

Over the coming months, works will increase as we continue rail bridge construction, build your new Mordialloc Station and upgrade the station precinct, build new pedestrian connections, public spaces, traffic signals, bus bays and carparks.

During this time, we’ll:

  • upgrade Albert Street with new kerbs, footpaths, traffic signals and bus bays
  • start work on the new signalised intersection with three signalised pedestrian crossings at the Nepean
  • Highway/Hearle Avenue intersection, by installing underground services and traffic signals
  • build a new roundabout at the Station Street/Pine Crescent intersection
  • continue piling, rail bridge construction and station precinct works
  • deliver and install large, prefabricated station buildings and materials
  • install cables and remove overhead wires in the rail corridor.

We’re also preparing the location of the new rail passenger car park, behind Main Street. As part of this, we’re removing 5 date palm trees, which Kingston City Council will relocate to Aspendale Gardens.

Our usual working hours at this stage of construction are Monday to Sunday, 7am to 7pm. We’ll make every effort to complete these works on schedule, however dates are subject to change.

What to expect

  • increased construction activity, machinery, vehicles, workers.
  • changes to parking, short term and intermittent road closures, extended detours and some delays.
  • additional lighting at night near works areas, directed away from residential properties where possible.
  • noticeable construction noise, dust and vibration near works areas.

There may be temporary utility service interruptions. Utility companies are responsible for notifying customers of any interruptions. Please contact your utility provider if you have any questions.

Upcoming nightworks

To complete essential road and rail bridge works, we are working 24/7 at times over the coming months. Works will take place both inside and surrounding the rail corridor between Como Parade West, Parkdale and Eulinga Avenue, Aspendale. We’ll be in touch with directly impacted residents in advance.

To remove the McDonald Street level crossing, Albert Street and McDonald Street will be closed to vehicles and pedestrians at times overnight and sometimes for longer periods in the coming months. We’ll notify the community ahead of time.

Parking and road changes in Aspendale

We’re making improvements to the local road network that will help traffic and pedestrians move smoothly and safely through the local area once the Station Street, Aspendale level crossing is removed. When the new rail bridge is built, drivers will no longer cross the rail line at Station Street. They will instead travel under the rail bridge at a new link road to the Nepean Highway, near Hearle Avenue.

To support this change, in March we’re building a roundabout at Station Street, near the Pine Crescent
intersection. We’ll also begin to install a signalised intersection with three signalised pedestrian crossings at the Nepean Highway/Hearle Avenue intersection.

We will be in touch with residents in this area with more specific information.

Parking on Nepean Highway and Hearle Avenue

Safety is a priority for the project. To ensure traffic changes are safe for all road and path users, space for some street parking needs to be reduced nearby. This information was first notified to the community in April 2025:

  • Room for up to 18 cars within the parking lane on Nepean Highway will be removed from just south of Hearle
  • Avenue to Watkins Street to allow for the required road width near the new signalised intersection.
  • Parking for up to 3 cars on Hearle Avenue, east of Hearle Lane, will be reduced to room for one car to allow vehicles to safely pass one another at the traffic lights.

Find out more in our ‘Local parking changes’ fact sheet.


Changes to the way you travel

Please follow signage and detours. Traffic management will be in place to safely guide you through the area.

Mordialloc

McDonald Street

  • Third party electrical works from Wednesday 11 March to Sunday 15 March:
    • Full road closure between Main Street service Road and Albert Street. Local access maintained.
    • Detours via White Street and Edithvale Road. The utility provider will notify in advance.
  • Installation of rail infrastructure and oversized deliveries at times until late 2026:
    • Intermittent lane closures between Albert Street and Nepean Highway/Main Street Service Road.
    • Pedestrian access over the rail line via Bear Street pedestrian crossing at times during this time.

Albert Street

  • Construction of the new rail bridge and Mordialloc Station, new bus bays, and pedestrian crossings and oversized deliveries from Monday 2 March to late April:
    • Northbound lane closed 24/7, between McDonald Street and Bear Street.
    • One way traffic (southbound) from McDonald Street to Bear Street.
    • Detour via Barkly Street. Traffic management in place. Local access and bus stops maintained.
  • Construction of the new rail bridge and Mordialloc Station, and oversized deliveries at times from Monday 2 March to late April, between 7am and 7pm:
    • Road closed at times between McDonald Street and Lewis Street.
    • Traffic management in place. Local access maintained.

Mordialloc Station car park

  • Relocating 5 date palm trees (working with Kingston City Council) from Wednesday 11 March to Friday 13 March:
    • Approximately 20 station car parks unavailable. Pedestrian detours in place.

Aspendale

Nepean Highway

  • Construction of new intersection from Monday 2 March to Tuesday 31 March
    • Removing up to 18 car spaces for the new intersection.
    • Temporary lane and parking closures between Station Street and Kara Grove, traffic management in place. Local traffic will have driveway access. Please plan ahead in case of delays.

Station Street

  • Construction of new roundabout from Monday 16 March to Wednesday 1 April:
    • Station Street closed between Attenborough Road and James Avenue. Detours via James Avenue and Eulinga Avenue.
    • Temporary no standing zones on Mill Street, James Avenue and Eulinga Avenue.
    • Local traffic will have driveway access, Please plan ahead in case of delays.
    • Pedestrians access maintained along Station Street, with minor detours and delays.
  • Roundabout works and panel installation at times in March:
    • Temporary lane closures between Attenborough Road and Eulinga Avenue.
  • Oversized deliveries at times until late 2026:
    • Intermittent road closures between Station Street level crossing and Eulinga Avenue.

Hearle Avenue

  • Building the new intersection on Monday 2 March:
    • Removing of up to 3 car spaces. Local access maintained.

Rail