31 March 2025

We’re making the Sunbury Line level crossing free in 2025, a year ahead of schedule, removing 8 dangerous and congested level crossings to improve safety, reduce congestion and run more trains, more often.

What we’re doing

In April, we'll continue to:

  • construct the shared use path including ramps and stairs to the road bridge
  • construct the new road bridge
  • install essential services, including drainage and public lighting
  • install concrete bridge barriers, road kerb and screening along the new bridge
  • prepare for landscaping works to take place from April until late 2025
  • remove site buildings from our satellite compound near Nottingham Way.

What to expect

  • Traffic management will be in place, including lane closures and reduced speed limits at times.
  • Deliveries including large concrete barriers and materials.
  • Machinery in the area including cranes and delivery trucks.
  • Increased construction noise and light in the area.
  • Where appropriate, we’ll be in touch with directly impacted stakeholders ahead of works.
  • To safely relocate existing services including public lighting, there will be a pedestrian detour on the corner of Calder Park Drive and Manchester Drive at times until late 2025.
  • Access to properties and local businesses will be maintained.
  • Our general working hours are Monday to Friday, 7am to 6pm and Saturday 7am to 5pm.

Note: The above dates and times may vary if our works are disrupted due to weather conditions or unforeseen circumstances.