28 February 2025
We’re making the Sunbury Line level crossing free in 2025, a year ahead of schedule, removing 8 dangerous and congested level crossings to improve safety and reduce congestion.
What we’re doing
We’re closing Calder Park Drive between Glenbruar Drive/Manchester Drive roundabout and the Calder Freeway from midnight Wednesday 12 March to 11.59pm Sunday 16 March.
During this time, we will install 9 large concrete beams to continue forming the new road bridge deck.
We’ll also be working nights only in the rail corridor from Monday 3 March to Wednesday 5 March, 9pm to 4am each night to complete overhead wiring works.
We’ll continue with works to:
- construct the shared use path
- install essential services, including drainage and public lighting
- install concrete bridge barriers, road kerb, screening and guardrail along the new bridge
- install overhead wiring and steel structures in the rail corridor.
What to expect
- Traffic management will be in place, including a road closure, lane closures and reduced speed limits at times.
- Deliveries including large concrete beams and materials.
- Machinery in the area including a large crane and delivery trucks.
- Increased construction noise and light in the area. We aim to minimise noise and light spill as much as possible.
- We’ll be in touch with directly impacted stakeholders ahead of works.
- Access to properties and local businesses will be maintained.
- To safely relocate existing services including public lighting, there will be a pedestrian detour on the corner of Calder Park Drive and Manchester Drive at times until late 2025.
- Access to properties and local businesses will be maintained.
- Our general working hours are Monday to Friday, 7am to 6pm and Saturday 7am to 5pm.
Disruptions
Road
- Calder Park Drive will be closed between Glenbruar Drive/Manchester Drive roundabout and the Calder Freeway from midnight Wednesday 12 March to 11:59pm Sunday 16 March. Detour via Kings Road and Melton Highway.
- There may be lane closures and reduced speed limits on Calder Park Drive at times, please refer to traffic management.
Rail
- Buses replace trains between North Melbourne and Sunbury from 8:30pm to last service each night, from Monday 3 March to Wednesday 5 March.
- From Monday 3 March to Wednesday 5 March, night works will be occurring in the rail corridor each night between 9pm and 4am.
Maps
Keeping you informed
- Text ‘CALDER’ to 0436 483 603 for SMS alerts on traffic and construction impacts.
- Subscribe for email updates
- Contact our 24/7 call centre on 1800 105 105 or contact@levelcrossings.vic.gov.au.
- Visit our project page, view upcoming disruptions and see our latest image gallery.
- For languages other than English please call 9209 0147