29 April 2025
We’re making the Sunbury Line level crossing free in 2025, a year ahead of schedule, removing 8 dangerous and congested level crossings to improve safety, reduce congestion and run more trains, more often.
What we’re doing
In May, we’ll be:
- installing concrete bridge barriers, road kerb and screening along the new road bridge
- painting concrete panels, piers, barriers and abutments
- constructing the shared user path, including ramps and stairs
- undertaking landscaping works
- installing essential services, including drainage and public lighting
- packing down our satellite site compound near Nottingham Way.
What to expect
- Traffic management will be in place, including lane closures and reduced speed limits at times.
- Deliveries including large concrete barriers and materials.
- Machinery in the area including cranes and delivery trucks.
- Increased construction noise and light in the area.
- Where required, we’ll be in touch with directly impacted stakeholders ahead of works.
- To safely relocate existing services including public lighting, there will be a pedestrian detour on the corner of Calder Park Drive and Manchester Drive at times until late 2025.
- Access to properties and local businesses will be maintained.
- Our general working hours are Monday to Friday, 7am to 6pm and Saturday 7am to 5pm.
Note: The above dates and times may vary if our works are disrupted due to weather conditions or unforeseen circumstances.
Pedestrian detour map
Keeping you informed
- Text ‘CALDER’ to 0436 483 603 for SMS alerts on traffic and construction impacts.
- Subscribe for email updates
- Contact our 24/7 call centre on 1800 105 105 or contact@levelcrossings.vic.gov.au.
- Visit our project page, view upcoming disruptions and see our latest image gallery.
- For languages other than English please call 9209 0147