20 May 2026

We’re removing the level crossing at Maidstone Street, Altona by building a new road bridge over the rail line to improve safety and create better connections.

Major construction is underway. Thank you for your patience as we deliver this important project.

What we’re doing

In June, we’ll continue:

  • constructing the bridge deck, including lifting the next set of beams into place
  • building the new temporary road along the north-eastern side of Maidstone Steet, which will open to traffic from 7am, Monday 22 June and will remain in place while we continue major construction
  • relocating underground power, gas, sewer, water and telecommunication services along Maidstone Street and surrounding roads. We are working closely with service providers who will communicate with you directly if services, or access, are affected.

Buses replace trains on the Werribee and Williamstown lines in May and June. For more information, please visit the Transport Victoria website.


Changes to the way you travel

Road

Maidstone Street

Closed to traffic between Jordan Close and north of the Maidstone Street level crossing:

  • each night from 8pm to 6am, from Tuesday 16 June to Thursday 18 June
  • 24/7 from 8pm, Friday 19 June to 6am, Monday 22 June.
  • Detours will be in place via Kororoit Creek Road, Millers Road and Civic Parade. Please see the detour map overleaf.
  • There will be no pedestrian access over the rail line along Maidstone Street during this time.

Ajax Road, Slough Road and Maidstone Street

  • Access to businesses on Ajax Road, Slough Road and Maidstone Street will be maintained under traffic management.
  • Only vehicles larger than a 19m semi-trailer and emergency services, will be granted access through the road closure from Kororoit Creek Road via a traffic control escort.
  • Delays of up to 90 minutes may be experienced whilst asphalt is being laid. Please allow extra travel time.
  • All other vehicles will need to follow the detour routes and will be granted access from south of the level crossing via a traffic control escort.

24/7 works

We’ll work outside of normal construction hours during the following times:

  • each night from 8pm to 6am, Tuesday 16 June to Thursday 18 June to tie-in the temporary road
  • 8pm, Friday 19 June to 3am, Monday 22 June to install new rail infrastructure inside the rail corridor
  • During these works, noise and vibration levels are not expected to be highly disruptive. Traffic management and light towers will also be in place.

What to expect

  • Normal working hours are Monday to Friday between 7am and 6pm and Saturday between 7am and 3pm.
  • Reduced speed limits and traffic management will be in place around our work areas, resulting in delays at times. Please follow all directional signage and travel safely when moving through the area.
  • Increase in construction vehicles, delivery trucks and machinery moving around the area.
  • Traffic management and light towers in place to ensure works can occur safely.
  • During some activities you may notice an increase in construction noise, vibration and dust.