5 March 2026
Works are progressing along the Eastern Freeway with new flyover ramps forming in Bulleen and the second half of the Doncaster Road bridge underway.
After a successful weekend closure of the citybound freeway lanes in early February, we've now shifted traffic to establish a major worksite in the middle of the freeway between Doncaster and Bulleen roads.
We've now lifted more than 30 of 188 steel beams that will form the elevated ramps connecting the Eastern Freeway to the North East Link tunnels.
We're continuing to build noise walls in 2026, with some completed panels now up between Estelle Street bridge and Elgar Road, south of the freeway.
When are we working? Day works - 7am to 6pm from Monday to Friday and 7am to 3pm Saturdays and Sundays Night works - 6pm to 7am from Monday to Saturday, 3pm to 6am Saturdays Day / night works at times during day and night works hours 24-hour works (at times) - Notification provided before works. We use water carts and noise mitigation measures wherever possible to reduce dust and noise while we work. We'll be in touch with impacted residents regarding specific times for construction activities and to offer support.
Upcoming disruptions in Bulleen We'll close the Eastern Freeway in both directions between Bulleen and Doncaster roads from 10pm, Friday 27 March to 5am, Monday 30 March .
We'll also close sections of the Eastern Freeway overnight in March and April as we continue to build the new interchange at Bulleen Road.
As part of construction of the Manningham Road interchange, there’ll be lane and road closures on Bulleen Road between Bridge and Avon streets for up to two weeks in April to complete critical drainage works.
To stay up to date visit Disruptions .
Eastern Freeway upcoming works (Zone map)- January 2026
Eastern Freeway map
Eastern Freeway Zoned map, including worksite area.
Map_Zone 1
Zone 1: Burke to Bulleen roads and Bulleen Road interchange
Activity Day works:
Piling in freeway centre median and next to Koonung Creek. Day/night works:
Delivery and installation of concrete and steel beams. Tree clearing, earthworks and drainage. Night works:
Bridge strengthening works on Bulleen Road bridge. What to expect Overnight lane and ramp closures Pedestrian and shared path detours Medium to low night time levels of noise, dust and vibration Use of directional lighting Delivery of heavy machinery and vehicles.
Activity Night works:
Asphalting, line marking and removal of traffic islands. Earthworks and drainage. What to expect Overnight lane and ramp closures Use of directional lighting.
Activity Day/night works:
Piling works to build retaining and noise walls, underpass connections and bridge foundations. Drainage, asphalting, permanent barrier construction and line marking. Traffic signal and drainage relocation works near Bulleen Road citybound entry ramp. Switching traffic onto temporary citybound exit ramp. Night works:
Installation of cabling for new on-road technology. What to expect Overnight lane and ramp closures Medium to low night time levels of noise, dust and vibration Heavy machinery and vehicles Traffic controllers and signage. Increase in heavy vehicles and machinery accessing site via Highview Road
Activity Day works:
Piling works to build retaining wall and noise walls. Day/night works:
Drainage works under freeway Installation of cabling for new on-road technology. Night works:
Asphalting, earthworks, barrier realignment and line marking. Installation of noise wall panels along freeway citybound. What to expect Overnight freeway, lane and ramp closures Traffic and shared path changes between Musca Reserve and Columba Street Medium to low night time levels of noise, dust and vibration Use of directional lighting Heavy machinery and vehicles.
Map_Zone 2
Zone 2: Bulleen to Doncaster roads and Koonung Creek Reserve
Activity Day works:
Construction of sewer shafts and pipe installation on Estelle Street. Construction of ramp at Bulleen Park and Ride. Construction of retaining wall at Kampman Street. Earthworks and installation of underground supports to build retaining wall at Estelle Street. Piling to build retaining wall at Park Avenue. Day/night works
Concrete barrier installation near the Ringwood-bound exit ramp. Piling for Ringwood-bound freeway retaining walls. Finishing works on Estelle Street bridge. Earthworks and removal of concrete pipes as part of sewer works. Concrete and steel fixing works for new freeway ramps and barriers. Night works:
Installation of cabling for new on-road technology under freeway Site and freeway investigations, asphalting, barrier realignment and line marking. Installation of noise wall panels along freeway citybound. What to expect Partial closure of Estelle Street, with detours in place Medium to low night time levels of noise, dust and vibration Use of directional lighting 24/7 operation of pump system at Willow Bend and Park Avenue Access and use of Koonung Creek Reserve worksite day and night Overnight citybound freeway closures
Activity Day works:
Piling works for new overhead signage and structures. Day/night works:
Relocating, decommissioning and installing utilities. Foundation and piling works for new express busway underpass. Earthworks, drainage, pavement and retaining wall works. Foundation and piling works for Ringwood side of new Doncaster Road bridge. Installation of footings near High Street for Sentinel statue. Piling for shared path underpass. Concrete formwork and pours for overhead signage near Ringwood-bound exit ramp. Earthworks near Doncaster Road citybound entry ramp. What to expect Overnight lane and ramp closures Pedestrian and shared path detours Medium to low night time levels of noise, dust and vibration Use of directional lighting Heavy machinery and vehicles Traffic controllers and signage.
Map_Zone 3
Zone 3: Doncaster to Tram roads and Valda Wetlands
Activity Day works:
Construction of hardstand near Massey Street. Day/night works:
Piling, concreting, steel works, earthworks, and installation of underground supports and concrete safety barriers to build retaining walls. Installation of concrete structures to protect creek. Concrete foundations to build new Doncaster Park and Ride. Installation of cabling for new on-road technology. Installation of water pipes and hydrant mains. Construction of retaining and noise walls. Night works:
Earthworks and installation of traffic barriers. Remove and install asphalt for new freeway lanes. 24/7 works:
24 Concrete and steel fixing works to build new traffic safety barriers. What to expect Overnight lane and ramp closures Medium to low night time levels of noise, dust and vibration Heavy construction vehicles and machinery entering and exiting site via Wilsons Road and Stanton Street Traffic controllers and signage Access to Doncaster Park and Ride site day and night Overnight machinery and material deliveries via freeway
Activity Night works:
Earthworks, and installation of traffic barriers. Installation of cabling for new on-road technology. 24/7 works:
Barrier realignment near Elgar Road citybound entry ramp. Installation of drainage under freeway. Installation of stairs, seats, lighting and handrails, painting and finishes on the Heyington Avenue bridge. Piling, concreting and steel works to support installation of retaining walls, noise walls and concrete structures. What to expect Overnight freeway, lane and ramp closures Shared path detours Medium to low night time levels of noise, dust and vibration Heavy vehicles and machinery accessing site via Clifton and Sweyn streets Overnight machinery and material deliveries via freeway.
Activity Day/night works:
Remove base of existing noise wall along Sargent Street. Night works:
Installation of cabling for new on-road technology. Installation of water pipes and hydrant mains. Installation of drainage at Sargent Street. 24/7 works:
24 Installation of concrete structures. Installation of underground supports, piling, concreting, steel works and earthworks. Construction of retaining and noise walls. What to expect Medium to low night time levels of noise, dust and vibration Heavy vehicles and machinery entering via Elgar Road Service Road and exiting via Doncaster Road citybound exit ramp
We're here to help We understand that construction in your local area can be challenging.
Call 1800 105 105 anytime or visit the Project Information Centre at 284 Doncaster Road, Balwyn North, Tuesday to Thursday, 9am to 3pm.