4 August 2025

We're reimagining the Valda Wetlands by rebuilding and revitalising parklands, wetlands and waterways. We’ll close the freeway between Doncaster and Tram roads for a weekend in early September to install a new Heyington Bridge for improved walking and cycling connections over the Eastern Freeway.

What we're doing

From July to September, we'll:

  • build new sewer shafts before relocating existing sewer mains
  • continue earthworks to shape the new wetlands
  • build concrete foundations for new noise walls during the day
  • install protective archways for the realigned Koonung Creek
  • deliver and assemble steel beams at night to form the new bridge structure
  • install bridge structures and ramps
  • install supporting structures and segments of the new bridge
  • mobilise a 600-tonne crane and perform a test lift of the new bridge
  • build concrete foundations in Stanton Street Reserve and install structures for the new bridge
  • complete concrete works for the bridge foundations in Stanton Street Reserve
  • close the freeway for a weekend in September to demolish the existing bridge and install the new bridge.

When we'll work

Day works: 7am to 6pm Monday to Friday and 7am to 3pm Saturdays

Night works: 7pm to 6am from Monday to Friday

What to expect

  • Construction vehicles, machinery and workers in the area
  • Medium levels of noise, dust and vibration from machinery and equipment.

Managing impacts

We carefully manage our works in line with the project's strict environmental performance requirements, including:

  • monitoring noise, dust and vibration levels with real time monitoring
  • preventing dust and water runoff with environmental controls
  • use of directional lighting when working at night.

If you have any concerns about these impacts, please contact the project team on 1800 105 105 any time.

Upcoming disruptions to the Eastern Freeway


In the coming months, there will be significant disruptions to the Eastern Freeway as we install new walking and cycling bridges between Burke Road and Tram Road. Check on-road signage and follow detours.

Stay up to date with the latest disruptions information

As works progress, we've started sending out weekly email updates to ensure that you have the latest information on upcoming night works.

Sign up to our e-newsletter

Get the latest project updates and information via email: bigbuild.vic.gov.au/roads-subscribe

Sign up for SMS updates

Receive updates directly to your phone. Text your suburb name to: 0447 251 237

Visit bigbuild.vic.gov.au/disruptions for the latest disruptions.

Schedule is subject to change. Visit bigbuild.vic.gov.au/works for schedule changes. For more information call 1800 105 105 or visit the Project Information Centre at 284 Doncaster Road, Balwyn North.

For languages other than English please call 9209 0147.


Sign up for updates

Receive updates about Eastern Freeway Upgrades.

Subscribe

Help us improve the website by completing a short survey

Close