24 August 2023

Extended work hours for the Lower Plenty Road interchange

In order to safely progress critical works on the North East Link Tunnels, we’re extending our evening working hours at the Lower Plenty Road interchange.

What you need to know

Extended work hours from:

Day

7am to 6pm, Monday to Friday and 7am to 3pm, Saturdays.

Night

6pm to 7am, Monday to Friday.

WhereWhenActivity What to expect

Kay and Debra Courts, Coleen and Borlase Streets and Lower Plenty Road

Until late 2024
  • Continue tunnel wall construction, including excavation and concrete pours.
  • Tunnel construction at night during the week.
  • Noise, vibration and dust from construction activities.

Map of work are

Download the notification to view the map of works area PDF, 393.4 KB

More information

From late August, crews will continue working into the night to safely build the tunnel walls, including excavation and concrete pours. Continuous pouring of concrete is required at times to achieve the correct structural quality in the concrete, to meet Australian standards.

Keeping in touch

We’ll be out talking to nearby residents and businesses about these works in more detail, including how we’ll be managing any local impacts. If you have any questions now, please contact the NELP 24/7 Contact Centre on 1800 105 105.


Schedule is subject to change. Visit our work notices page for schedule changes. For more information call 1800 105 105 or visit the Hub at 17 Watsonia Road, Watsonia.