24 January 2025 to 28 February 2025

Works are underway in Burwood to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday.

Night works 6pm to 7am Monday to Sunday.

Extended works 6am to 10pm Monday to Saturday.

The following works will be carried out during February.

WhereWhen What we are doing What to expect
SRL site compoundExtended works: Ongoing to 2025
  • Building a tunnel access structure
  • Medium levels of noise and dust
  • Light spillage
Burwood Highway, Burwood

Westbound
Day works: Ongoing to mid 2025

Night works: From Tuesday 11 February for up to 5 nights
  • Moving underground services
  • Roadworks
  • Overnight road closure between McIntyre Street and Peacock Street from 11 February for up to 5 nights
  • Double lane closures between McIntyre Street and Peacock Street
  • Pedestrian detours

Changed traffic conditions will continue until mid 2025. We will continue to communicate these changes in advance

Coppard Street, Cumming Street, BurwoodDay works: From Tuesday 11 February to March 2025
  • Transporting site materials
  • Frequent truck movements during daytime hours
  • Up to 53 car spaces closed
  • Medium levels of noise, dust and vibration
Sinnott Street,  BurwoodDay works: Ongoing to mid-2025
  • Moving underground services
  • Transporting site materials
  • Traffic management in place between Corrigan Road and Highbury Road
  • Frequent truck movements during daytime hours
  • Up to 40 car spaces closed
  • Pedestrian detours
Network Support Facility Site,Extended works: Ongoing to mid-2025
  • Building structures for the Network Support Facility
  • Medium levels of noise, dust and vibration
Highbury Road, BurwoodDay works: Ongoing to mid 2025
  • Moving underground services
  • Transporting site materials
  • Lane closures between Ireland Street and Gillard Street
  • Medium levels of noise, dust and vibration
  • Pedestrian detours

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Maintaining access to businesses and homes
  • Transporting materials from site in covered trucks to minimise dust
  • Installing road safety and detour signage
  • Positioning light towers away from properties
  • Monitoring noise, dust and vibration levels
  • Turning off equipment when not in use
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Burwood.