11 April 2025 to 1 June 2025

Works are underway in Burwood to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works: 6pm to 7am Monday to Saturday
24 hour works: 7am Monday to 7am Sunday

The following works will be carried out during May.

WhereWhen What we are doing What to expect
SRL site compound 24 hour works: Ongoing until September
  • Building a tunnel access structure
  • 24/6 works until September
  • Medium levels of noise and dust
  • Light spillage
Burwood Highway, Burwood

Westbound
Day works: Ongoing until mid 2025

Night works: Ongoing until Monday 19 May
  • Moving underground services
  • Road modification works
  • Overnight road closures between McIntyre Street and Peacock Street for up to 15 nights
  • Double lane closures between McIntyre Street and Peacock Street
  • Pedestrian detours

Changed traffic conditions will continue until mid 2025. We will continue to communicate these changes in advance

Burwood Highway, Burwood

Eastbound
Day works: Ongoing until Monday 19 May

Night works: Ongoing until Monday 19 May
  • Road modification works
  • Overnight road closures between Elgar Road and Holland Avenue for up to 15 nights
  • Double lane closures between Elgar Road and Holland Avenue
  • Pedestrian detours
Coppard Street, Cumming Street, Burwood Day works: Ongoing until mid 2025
  • Transporting site materials
  • Frequent truck movements during daytime hours
  • Up to 53 car spaces closed
  • Medium levels of noise, dust and vibration
Sinnott Street, Burwood Day works: Ongoing until late 2025
  • Moving underground services
  • Transporting site materials
  • Road closures in stages until July
  • Frequent truck movements during daytime hours
  • Up to 40 car spaces closed
  • Pedestrian detours
Network Support Facility Site, 24 hour works: Ongoing until late 2025
  • Building structures
  • Low to medium levels of noise, dust and vibration
Highbury Road, Burwood Day works: Ongoing until mid 2025
  • Moving underground services
  • Lane closures in stages between Ireland Street and Gillard Street
  • Medium levels of noise, dust and vibration
  • Pedestrian detours

Traffic disruptions are subject to change due to conditions outside of our control.

Check the map

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to community by:

  • Maintaining access to businesses and homes
  • Transporting materials from site in covered trucks to minimise dust
  • Installing road safety and detour signage
  • Positioning light towers away from properties
  • Monitoring noise, dust and vibration levels
  • Turning off equipment when not in use
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Burwood.