Works are underway in Clayton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works: 6pm to 7am Monday to Saturday
Extended works: 7am to 1pm Sunday

WhereWhen What we are doing What to expect
Clayton Road, Clayton Day/night and extended works: Ongoing until late February
  • Site establishment
  • Moving underground services
  • Intermittent lane and overnight road closures between Shandeau Avenue and Carinish Road
  • Northbound lane and footpath closure between Haughton Road and Colonel Street
  • Access for emergency vehicles and buses maintained
Carinish Road, Clayton Day/Night and extended works: From 31 January
  • Site establishment
  • Permanent closure of Carinish Road (see below)
  • Road and footpath closure between Link Road and Clayton Road
Haughton Road, Clayton Day/night works:  From early to late February
  • Site establishment
  • Shared user path construction
  • Overnight road closure between Link Road and Clayton Road for up to 3 nights
  • 21 on-street parking spaces closed
  • Eastbound closure between Link Road and Clayton Road

Link Road, Clayton

Day/night works: From early to late February

  • Site establishment
  • Overnight road closure for up to 3 nights
  • Road closure for up to 2 weeks in mid February
Shandeau Avenue, Clayton Day/night works: Ongoing until mid February
  • Upgrading the intersection at Clayton Road
  • Road closure for up to 2 weeks
  • Overnight closure of Dixon Street intersection for up to 2 nights

Madeleine Road, Clayton

Day/night works: Ongoing until late March
  • Site establishment
  • Driveway construction
  • Intermittent road and lane closures between Lillian Street and Carinish Road
  • On-street parking space closures

SRL worksite west of  Clayton Road, Clayton

Day/night and extended works: Ongoing until late March
  • Site establishment
  • Safe removal of hazardous materials
  • Tree removal
  • Moderate levels of noise, dust and vibration
  • Increased truck movements

Changes to Carinish Road

Tunnel boring machines to build the SRL East tunnels will launch in 2026. To prepare for building the new underground station, we're protecting the elevated rail line, permanently closing a portion of Carinish Road from 31 January, and upgrading Shandeau Avenue. Click here to learn more.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

  • Maintaining access for emergency vehicles and buses at all times
  • Maintaining access to homes and businesses
  • Safely removing hazardous materials in accordance with Environmental Protection Authority regulations
  • Transporting materials from site in covered trucks to minimise dust
  • Using water and dust suppressants
  • Installing road safety and detour signage.