1 January 2025 to 31 January 2025

Works are underway in Clayton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday

Night works: 6pm to 7am Monday to Saturday

Extended works: 1pm to 6pm Saturday and 7am to 6pm Sunday

WhereWhen What we are doing What to expect
Clayton Road Day/night and extended works: From mid January until late February
  • Site establishment
  • Moving underground services
  • Intermittent lane and overnight road closures between Shandeau Avenue and Carinish Road
  • Pedestrian detours
  • Access for emergency vehicles and buses maintained
Carinish Road Day/Night works: Ongoing from mid January
  • Site establishment
  • Implementing permanent closure of Carinish Road
  • Road and footpath closure between Link Road and Clayton Road
  • Pedestrian detours
Haughton Road Day/night works:  From late January until late February
  • Site establishment
  • Moving underground services
  • Overnight road closure for up to 3 nights
  • 21 on-street parking spaces closed
  • Parallel parking to be installed
  • Shared user path detours in place
Shandeau Avenue Day/night works: From mid January until early February
  • Upgrading the intersection at Clayton Road
  • Road closure for up to 2 weeks
  • Overnight closure of Dixon Street intersection for 2 nights in late January
  • Local access maintained

Link Road

Day/night works: Late January

  • Site establishment
  • Lane closed eastbound between Thomas Street and Pullyn Street during the day for up to 5 days
  • Intermittent overnight road closures between Clayton Road and Thomas Street for up to 6 nights
  • On-street parking space closures
  • Local access maintained
  • Bus services maintained

Madeleine Road

Night works: From mid to late January
  • Moving underground services
  • Road closure at the Carinish Road intersection for up to 10 nights
  • Local access maintained

SRL worksite between Clayton Road and Madeleine Road

Day works: Ongoing until mid 2025
  • Site establishment
  • Safe removal of hazardous materials
  • Moderate levels of noise, dust and vibration
  • Increased truck movements

Changes to Carinish Road and Shandeau Avenue

Tunnel boring machines to build the SRL East tunnels will launch in 2026. To prepare for building the new underground station, we're protecting the elevated rail line, permanently closing a portion of Carinish Road from 31 January, and upgrading Shandeau Avenue. Click here to learn more.

Clayton shopping precinct remains open and accessible during these works.

There are no SRL works during the holiday period from Saturday 21 December to Sunday 5 January inclusive.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

  • Maintaining access for emergency vehicles and buses at all times
  • Maintaining access to homes and businesses
  • Safely removing hazardous materials in accordance with Environmental Protection Authority regulations
  • Transporting materials from site in covered trucks to minimise dust
  • Using water and dust suppressants
  • Installing road safety and detour signage.