29 August 2024 to 29 September 2024

Glen Waverley施工最新消息(PDF 2.5MB)

Works are underway in Glen Waverley to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday and Sunday

Night works: 6pm to 7am Monday to Saturday

Extended works: 1pm to 3pm Saturday.

The following works will be carried out during September.

Stage 1

WhereWhen What we are doing What to expect
Myrtle Street, Glen Waverley Day/Extended works: Ongoing to late 2024
Night works: From early-September for up to 14 nights
  • Establishing a worksite
  • Moving underground
    services
  • Safely removing hazardous material
  • Road closure between Coleman Parade and Bogong Avenue
  • Pedestrian detours
  • Medium levels of noise
Montclair Avenue, Glen Waverley Day/Extended works: Ongoing to mid-September
Night works: From early-September for up to 14 nights
  • Installing an additional access point to Glendale Street car park
  • Moving underground services
  • Removing vegetation including up to 21 trees
  • Road closure between Myrtle Street and Kingsway
  • Up to 15 car spaces closed in Glendale Street car park, including 2 accessible car spaces
  • Traffic management and pedestrian detours
  • Medium levels of noise
Railway Parade North car park, Glen Waverley Day/Extended works: Ongoing to late 2024
  • Establishing a temporary worksite
  • Moving underground services
  • Up to 100 car spaces closed
  • Traffic management and pedestrian detours
  • Medium levels of noise
Railway Parade North, Glen Waverley Day/Extended works: Ongoing to late 2024
  • Establishing a temporary worksite
  • Moving underground services
  • Road closure between Euneva Avenue and Kingsway
  • Up to 40 car spaces closed
  • Access to Glen Waverley Bus Station will be maintained
  • Traffic management and pedestrian detours
  • Medium levels of noise
  • Light spillage

Stage 2

WhereWhenWhat we are doingWhat to expect
Myrtle Street, Glen WaverleyDay/Extended works: Ongoing to late 2024
  • Establishing a worksite
  • Moving underground services
  • Safely removing hazardous material
  • Road closure between Coleman Parade and Montclair Avenue
  • Pedestrian detours
  • Medium levels of noise
Myrtle Street, Glen WaverleyDay/Extended works: Ongoing to early-October
Night works: From early-September for up to 14 nights
  • Establishing a worksite
  • Moving underground services
  • Road closure between Montclair Avenue and Bogong Avenue
  • Pedestrian detours
  • Medium levels of noise
Railway Parade North car park, Glen WaverleyDay/Extended works: Ongoing to late 2024
  • Establishing a temporary worksite
  • Moving underground services
  • Up to 100 car spaces closed
  • Traffic management and pedestrian detours
  • Medium levels of noise
Railway Parade North, Glen WaverleyDay/Extended works: Ongoing to late 2024
  • Establishing a temporary worksite
  • Moving underground services
  • Road closure between Euneva Avenue and Kingsway
  • Up to 40 car spaces closed
  • Access to Glen Waverley Bus Station will be maintained
  • Traffic management and pedestrian detours
  • Medium levels of noise
  • Light spillage
Coleman Parade, Glen WaverleyDay/Extended works: Mid-September to late 2024
Night works: From mid-September for up to 6 nights
  • Moving underground services
  • Road closure east of Carramar Avenue to Kingsway
  • Up to 60 commuter car spaces closed
  • Traffic management and pedestrian detours
  • Changes to 737 bus route (visit ptv.vic.gov.au to plan your journey)
  • Medium levels of noise
  • Light spillage
Glendale Street, Glen WaverleyDay/Extended works: Late-September to late 2024
Night works: From late-September for up to 3 nights
  • Moving underground services
  • Up to 15 car spaces closed within the Waverley RSL car park
  • Up to 30 car spaces closed within the Montclair Avenue car park

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Maintaining access to the Euneva Avenue, Euneva West, Waverley RSL, Glendale Street and Montclair Avenue car parks
  • Transporting materials from site in covered trucks to minimise dust
  • Installing road safety and detour signage
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Turning off equipment when not in use
  • Using noise blankets on equipment
  • Using water and dust suppressants
  • Minimising light spill
  • Coordinating disruptions with other construction companies in the area.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Glen Waverley.