Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.
We are building a Stabling Facility in Heatherton and preparing to launch Tunnel Boring Machines (TBMs) from Clarinda.
Upcoming works at these sites are summarised below:
Stabling Facility in Heatherton
Building the Eastern Tunnel Entrance (ETE) and Western Tunnel Entrance (WTE)
Building a permanent Network Support Facility (NSF) for construction and operational power
Moving underground and above ground services
Building a heavy vehicle access point into the Stabling Facility from Kingston Road.
Clarinda
Site investigations, site establishment and building a temporary power supply facility to power the TBMs.
What we are doing
Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday Night works: 6pm to 7am Monday to Friday Extended works: 6pm to 10pm Monday to Friday, 1pm to 5pm Saturday and Sunday. 24-hour works from late October.
Where
When
What we are doing
What to expect
Stabling Facility in Heatherton
Day/night/extended works: Ongoing to late December 2024
Building the ETE
Building the NSF
Site establishment
Demolition works
Site investigations
Preparing to build the WTE including earthworks, clearing trees and vegetation, safely removing hazardous materials, site investigations, drainage works and site establishment including staff facilities
Traffic barrier install and removal
Building a heavy vehicle access point from Kingston Road into the Stabling Facility
Building a temporary signalised pedestrian crossing over Kingston Road east of Nicholas Grove
Moderate levels of noise, vibration, light and dust
Kingston Walk Linear Reserve closed at Kingston Road due to nearby construction. Access is maintained via Nicholas Grove and Henry Street
Changed traffic conditions
There will be changed traffic conditions, including lane and road closures from mid-November to early-February on Elder Street South, Henry Street and Old Dandenong Road
There will be changed traffic conditions, including lane and road closures until late-December on Kingston Road
No works impacting Kingston Road will occur during the Australian Open Golf Golf tournament from 24 November – 4 December
Access to homes and businesses will be maintained
Drivers are advised to follow local traffic signage and allow extra travel time
Sign up for works reminders via SMS text to get traffic updates
Changes to local bus services
Weekday impacts to bus route 631 between Nicholas Grove and Pine Lane until late-December
Night and weekend impacts to bus route 631 between Dingley Bypass and Warrigal Road until late-December
Visit ptv.vic.gov.au to plan your journey
Stabling Facility in Heatherton
Day/night works: Ongoing to mid December 2024
N/A
Building a heavy vehicle access point from Kingston Road into the Stabling Facility including site establishment, earthworks, clearing trees and vegetation
Building a temporary signalised pedestrian crossing over Kingston Road east of Nicholas Grove
Installing Keep Clear linemarking on Kingston Road at Nicholas Grove and Golf View Road
Clarinda
Day works: Ongoing Night works: For up to 2 nights Extended works: For one weekend in early October
Earthworks, tree and vegetation removal, road modifications and site establishment to install a temporary power supply facility
Site fencing installation
Site establishment of staff facilities on Victory Road
Site investigations
Road lighting installation
Asphalting
Moderate levels of noise, vibration, light and dust
Changed traffic conditions
Peace Road closed day and night until mid-December
There will be changed traffic conditions during the day on Kingston Road at Peace Road from mid-November to mid-December. Traffic maintained in both directions
Overnight lane closures on Kingston Road between Dingley Bypass and Peace Road for up to two nights from mid-November to late-December. Traffic maintained in both directions
Changes to Kingston Walk Linear Reserve
Access into the Kingston Walk Linear Reserve will be closed at Kingston Road until late December 2024.
Access in and out of the reserve has been maintained at the northern end via Henry Street and Nicholas Grove
Note: Timing of works may change due to weather or ground conditions.
Grow Master, Diaco's and Kingston Heath Golf Club will be open for business during works.
Impacts
As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.
Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.
How we will manage our works
We will minimise impacts to the community by:
Transporting materials from site in covered trucks to minimise dust
Safely removing hazardous materials in accordance with EPA regulations
Scheduling works to reduce impacts
Maintaining access to homes and businesses
Monitoring noise, dust and vibration levels
Minimising light spill
Turning off equipment when not in use
Using noise blankets on equipment
Using water and dust suppressants.
Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.