11 October 2024 to 11 November 2024
Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.
We are building a Stabling Facility in Heatherton and preparing to launch Tunnel Boring Machines (TBMs) from Clarinda.
Upcoming works at these sites are summarised below:
Stabling Facility in Heatherton
- Building the Eastern Tunnel Entrance (ETE) and Western Tunnel Entrance (WTE)
- Building a permanent Network Support Facility (NSF) for construction and operational power
- Moving underground and above ground services
- Building a heavy vehicle access point into the Stabling Facility from Kingston Road.
Clarinda
- Site investigations and building a temporary power supply facility for the TBMs.
What we are doing
Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works: 6pm to 7am Monday to Friday
Extended works: 6pm to 10pm Monday to Friday, 1pm to 5pm Saturday and Sunday.
24-hour works from late October.
Where | When | What we are doing | What to expect |
---|---|---|---|
Stabling Facility in Heatherton | Day/night/extended works: Ongoing to late December 2024 |
|
Changed traffic conditions
Changes to local bus services
|
Stabling Facility in Heatherton | Day/night/extended works: Ongoing to late December 2024 |
| N/A |
Clarinda | Day works: Ongoing Night works: For up to 2 nights Extended works: For one weekend in early October |
|
|
It's important to note the timing of works may change due to weather or ground conditions.
Grow Master, Diaco's and Kingston Heath Golf Club will be open for business during works.
Impacts
As with all major infrastructure projects, surrounding communities may experience some impacts during construction.
The Project supports businesses and residents to continue to live, work, study and shop in their community.
Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.
How we will manage our works
We will minimise impacts to the community by:
- Transporting materials from site in covered trucks to minimise dust
- Removing hazardous materials in accordance with EPA regulations
- Scheduling works to reduce impacts
- Maintaining access to homes and businesses
- Monitoring noise, dust and vibration levels
- Minimising light to businesses and residents
- Turning off equipment when not in use
- Using noise blankets on equipment
- Using water and dust suppressants.
Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton.