25 August 2025 to 1 October 2025

Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Stabling Facility in Heatherton

  • Building the eastern tunnel entrance (ETE) and western tunnel entrance (WTE)
  • Building a permanent network support facility (NSF)
  • Moving underground and above ground services.

Tunnel Boring Machine (TBM) launch site, Clarinda

  • Building the Clarinda tunnel access structures (TAS)
  • Connecting underground services.

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Extended works: 6pm to 10pm Monday to Friday and 1pm to 10pm Saturday
Night works: 6pm to 7am Monday to Sunday
24 hour works: 7am to 7am Monday to Sunday

WhereWhen What we are doing What to expect

Train stabling facility west, Heatherton

Day works: Ongoing to late 2025
Extended works: Ongoing to late 2025
  • Building the WTE including earthworks, concreting, guide wall construction, diaphragm wall construction, and piling
  • Site investigations
  • Safe removal of hazardous material
  • To safely deliver works, some construction works including concrete pouring will need to be undertaken until 10pm
  • Workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Moderate levels of noise, vibration, light and dust
  • Truck movements and delivery of large machinery for up to 3 nights
Train stabling facility east, Heatherton 24 hour: Ongoing to late 2025
  • Building the ETE, with 24-hour excavation and related works
  • Building the NSF
  • Site investigations
  • Road reinstatement
  • Safe removal of hazardous material
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements
  • Changed traffic conditions on Elder Street with traffic management in place until mid September
Old Dandenong Road, Heatherton

Day/night works: Ongoing to late October 2025

  • Moving and connecting underground and above ground services
  • Intermittent northbound lane and road closures for up to 2 weeks between Kingston Road and Madden Road from early September to late October
  • Moderate levels of noise, vibration, light and dust
Kingston Road, Heatherton

Day/night works: Ongoing to late October 2025

  • Road reinstatement
  • Site deliveries
  • Moving and connecting underground and above ground services
  • Traffic barrier movements
  • Intermittent overnight road closures between Nicholas Grove and Clayton Road from late August to mid October
  • Intermittent westbound closures between Pine Lane and Dingley Bypass for up to 2 weeks from early September to late October
  • Changed traffic conditions between Nicholas Grove and Clayton Road with traffic management in place
  • Moderate levels of noise, vibration, light and dust
  • Changes to 631 bus route including closure of some bus stops between Nicholas Grove and Clayton Road
  • Visit ptv.vic.gov.au to plan your journey

Clayton Road, Clayton South

Day wors: Early September 2025
  • Site investigations
  • Changed traffic conditions between Victory Road and Ryans Road
TBM launch site, Clarinda24 hour:Ongoing to late 2025
  • Building the Clarinda TBM launch site, including civil works, concrete slab construction, site drainage install, diaphragm wall construction, piling and ground improvement
  • Changed traffic conditions on Peace Road and Victory Road
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements day and night

Note: Timing of works may change due to weather or ground conditions.

Local traders remain open for business during works.

  • Kingston Road between Nicholas Grove and Clayton Road
  • Henry Street at the intersection of Old Dandenong Road
  • Old Dandenong Road between Kingston Road and Madden Road
  • Peace Road between Kingston Road and Victory Road
  • Victory Road between Peace Road and Clayton Road
  • Clayton Road between Victory Road and Ryans Road
  • Labels describe:

    • Changed traffic conditions, including lane and overnight road closures on Kingston Road, between Nicholas Grove and Dingley Bypass. Follow traffic signage for detours.
    • Changed traffic conditions including lane and overnight road closures on Kingston Road, between Dingley Bypass and Clayton Road. Follow traffic signage for detours.
    ">

    Impacts

    As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

    Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

    How we will manage our works

    We will minimise impacts to the community by:

    • Covering trucks to minimise dust
    • Monitoring noise, dust and vibration levels
    • Using noise blankets and hoarding to minimise noise, dust and light spill
    • Safely removing hazardous materials in accordance with regulations
    • Using water and dust suppressants
    • Maintaining access to homes and businesses.

    Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.