28 June 2024 to 31 July 2024

Works are underway in Heatherton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday

Night works: 9pm to 7am Monday to Saturday

Extended works: 6am to 7am Monday to Saturday, 6pm to 10pm Monday to Friday and 1pm to 5pm Saturday until December 2024. 24-hour works for up to 3 days between late-July and early-August.

The following works will be carried out during July.

WhereWhen What we are doing What to expect
217 Kingston Road, Heatherton Day works: ongoing through July
Extended works: Ongoing through July
  • Earthworks
  • Safe removal of hazardous material
  • Construction of the eastern tunnel entrance
  • Site investigations
  • Extension of the site compound
  • Installing drainage
  • Traffic management in place on Old Dandenong Road
  • Extended works 6pm to 10pm Monday to Friday and 1pm to 5pm Saturdays until December 2024 to install concrete panels for the eastern tunnel entrance. There may be some low-level noise and light coming from the worksite during these works.
  • Extended works from 6am to 7am to line trucks for safe removal of hazardous materials
91-185 Kingston Road, HeathertonDay works: ongoing through July
  • Site investigations
N/A
Kingston Road, Heatherton and Kingston Road, ClarindaDay works/night: ongoing through July
Extended works: 24-hour works for up to 3 days between late-July and early-August
  • Building a new U-turn between Dingley Bypass and Peace Road
  • Asphalting
  • Line marking
  • Traffic barrier removal
  • Moving underground services
  • Installing power poles
  • Lane closures in both directions during the day and overnight between Dingley Bypass and Clayton Road until early-August
  • Overnight westbound lane closure between Dingley Bypass and Old Dandenong Road for up to 2 weeks from mid-July to late-July
  • Intermittent westbound traffic changes between Pine Lane and Old Dandenong Road from late-July for up to 2 days
  • 24-hour road closure between Dingley Bypass and Clayton Road for up to 3 days between late-July and early-August
  • Closure of Route 631 bus stops 19, 20, 48 and 49 for up to 3 days between late-July and early-August. Nearest available bus stops are located on Kingston Road and Clayton Road
  • Traffic management and detours will be in place

Elder Street South, Clarinda

Day works: From early-July to mid-July
  • Gate and signage installation
  • Intermittent lane closures in both directions between Old Dandenong Road and Hunt Crescent

Clarinda Road, Clarinda

Day works: From early-July to mid-July
  • Installing signage
  • Intermittent southbound lane closures between Bourke Road and Old Dandenong Road
Old Dandenong Road, HeathertonDay works: From early-July to mid-July
Night works: From mid-July to late-July
  • Installing signage
  • Moving underground services
  • Intermittent lane closures in both directions between Clarinda Road and Henry Street
  • Overnight southbound lane closure between Henry Street and Kingston Road for up to 2 weeks from mid-July to late-July
  • No southbound access from Old Dandenong Road across Kingston Road overnight for up to 2 weeks from mid-July to late-July
Dingley Bypass, ClarindaDay works: From early-July to late-July
Night works: From early-July to mid-July
  • Installing traffic barriers
  • Tree removal
  • Installing signage
  • Site investigations
  • Overnight northbound road closure between Clarinda Road and Kingston Road for up to 4 nights from early-July to mid-July
  • Intermittent lane closures in both directions north
    and south of Clarinda Road
  • Reduced speed limit near Kingston Road from mid-July for up to 1 week

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Transporting materials from site in covered trucks to minimise dust
  • Removing hazardous materials in accordance with EPA regulations
  • Scheduling works to reduce impacts
  • Installing road safety and detour signage
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Minimising light spill
  • Turning off equipment when not in use
  • Using noise blankets on equipment
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton.