1 September 2024 to 1 October 2024

Works are underway in Heatherton to prepare for tunnelling to begin in 2026 and future construction of the Stabling Facility.

Current works

  • Site establishment to set up a site compound and prepare for construction of the western tunnel entrance
  • Preparing to build a vehicle access point into the Stabling Facility from Kingston Road
  • Moving underground and above ground services
  • Construction of the eastern tunnel entrance to support tunnelling activities and allow trains to exit and enter the tunnel once operational
  • Locating underground services, soil and geotechnical investigations to prepare for future construction activities
  • Construction of the Stabling Network Support Facility to provide power during construction and operation of Suburban Rail Loop East.

Please follow traffic signage and detours in place whilst these works are occurring.

WhereWhenWhat we are doingWhat to expect
217 Kingston Road, HeathertonDay works: Ongoing through September

Extended works: Ongoing to late 2024
  • Earthworks
  • Safe removal of hazardous material
  • Construction of the eastern tunnel entrance
  • Construction of the Network Support Facility
  • Site investigations
  • Extension of the site compound
  • Installing drainage
  • Extended works to install concrete panels for the eastern tunnel entrance
  • Extended works to install concrete foundations, pre-cast panel walls and conduct electrical drilling for the Network Support Facility
  • Works may cause some low-level noise and light spillage
Old Dandenong Road, HeathertonDay works: Ongoing through September

Night works: From early-September for up to 4 nights
  • Traffic barrier placement
  • Moving underground water and
    power services
  • Road closure between Elder Street South and Kingston Road from early-September for up to 4 nights
  • Southbound lane closure between Elder Street South and Kingston Road until late-September
Henry Street, HeathertonDay works: Ongoing through September
  • Moving underground water and power services
  • Traffic barrier placement
  • Eastbound lane closure
Dingley Bypass Road Reserve, HeathertonDay works: Ongoing through September
  • Tree removal
  • Moving underground power services
  • Site investigations
  • Reduced speed limit near Kingston Road from early-September for up to 1 week
Old Dandenong Road and Kingston Road intersection, Heatherton

Night works:From early-September for up to 5 nights

  • Above ground power works
  • Traffic light testing
  • Kingston Road eastbound lane closure between Pine Lane and Old Dandenong Road
  • Old Dandenong Road northbound lane closure between Kingston Road and Henry Street
  • Works may cause some low-level noise and light spillage
91-185 Kingston Road, HeathertonDay works: From early-September
  • Ongoing investigations to identify potential presence of hazardous materials
  • Tree and vegetation removal
  • Earthworks
  • Site investigations
  • Site establishment
  • Earthworks and site establishment activities may generate some moderate noise, vibration and dust
Kingston Road, ClarindaNight works: From early-September to mid-September for up to 2 nights
  • Road lighting installation
  • Overnight single lane closures on Kingston Road between Dingley Bypass and Peace Road
Elder Street South, ClarindaDay works: From mid-September to late-September

Night works: From late-September for up to 4 nights
  • Moving underground power services
  • Traffic barrier installation and removal
  • Eastbound lane closure from mid-September to late-September
  • Overnight road closure from mid-September for up to 4 nights to install traffic barriers
  • Road closure between Old Dandenong Road and Elder Street South Reserve for up to 2 weeks from late-September
  • Access to properties and the Elder Street Reserve will be maintained
Kingston Road, HeathertonNight works: From mid-September for up to 1 night From late-September

Day works: From late-September for up to 5 nights
  • Site establishment
  • Site investigations
  • Traffic barrier placement
  • Preparing to install drainage
  • Power pole replacement
  • Installing Keep Clear line marking
  • Changed traffic conditions overnight between Ball Road and Nicholas Grove for 1 night in mid-September
  • Overnight road closure on Kingston Road between Golf View Road and Old Dandenong Road for up to 5 nights in late-September to install traffic barriers and Keep Clear line marking at Nicholas Grove and Golf View Road
  • Day and night lane closure between Nicholas Grove and Old Dandenong Road once traffic barriers are installed. Traffic will be maintained in both directions
  • Access to properties and businesses will be maintained

It's important to note the timing of works may change due to weather or ground conditions.

Old Dandenong Road Closure

Old Dandenong Road will be closed permanently from Tuesday 1 October 2024 for construction of the Stabling Facility. Further details will be shared closer to the date.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction.
The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Transporting materials from site in covered trucks to minimise dust
  • Removing hazardous materials in accordance with EPA regulations
  • Scheduling works to reduce impacts
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Minimising light to businesses and residents
  • Turning off equipment when not in use
  • Using noise blankets on equipment
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton.