1 September 2024 to 1 October 2024
Works are underway in Heatherton to prepare for tunnelling to begin in 2026 and future construction of the Stabling Facility.
Current works
- Site establishment to set up a site compound and prepare for construction of the western tunnel entrance
- Preparing to build a vehicle access point into the Stabling Facility from Kingston Road
- Moving underground and above ground services
- Construction of the eastern tunnel entrance to support tunnelling activities and allow trains to exit and enter the tunnel once operational
- Locating underground services, soil and geotechnical investigations to prepare for future construction activities
- Construction of the Stabling Network Support Facility to provide power during construction and operation of Suburban Rail Loop East.
Please follow traffic signage and detours in place whilst these works are occurring.
Where | When | What we are doing | What to expect |
---|---|---|---|
217 Kingston Road, Heatherton | Day works: Ongoing through September Extended works: Ongoing to late 2024 |
|
|
Old Dandenong Road, Heatherton | Day works: Ongoing through September Night works: From early-September for up to 4 nights |
|
|
Henry Street, Heatherton | Day works: Ongoing through September |
|
|
Dingley Bypass Road Reserve, Heatherton | Day works: Ongoing through September |
|
|
Old Dandenong Road and Kingston Road intersection, Heatherton | Night works:From early-September for up to 5 nights |
|
|
91-185 Kingston Road, Heatherton | Day works: From early-September |
|
|
Kingston Road, Clarinda | Night works: From early-September to mid-September for up to 2 nights |
|
|
Elder Street South, Clarinda | Day works: From mid-September to late-September Night works: From late-September for up to 4 nights |
|
|
Kingston Road, Heatherton | Night works: From mid-September for up to 1 night From late-September Day works: From late-September for up to 5 nights |
|
|
It's important to note the timing of works may change due to weather or ground conditions.
Old Dandenong Road Closure
Impacts
As with all major infrastructure projects, surrounding communities may experience some impacts during construction.
The Project supports businesses and residents to continue to live, work, study and shop in their community.
Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.
How we will manage our works
We will minimise impacts to the community by:
- Transporting materials from site in covered trucks to minimise dust
- Removing hazardous materials in accordance with EPA regulations
- Scheduling works to reduce impacts
- Maintaining access to homes and businesses
- Monitoring noise, dust and vibration levels
- Minimising light to businesses and residents
- Turning off equipment when not in use
- Using noise blankets on equipment
- Using water and dust suppressants.
Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton.