27 November 2026
to 1 December 2026
Box Hill 正在开展施工
Works are underway in Box Hill to deliver the Suburban Rail Loop (SRL) East.
What we are doing
Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works 6pm to 7am Monday to Sunday, as required
The following works will be carried out during December 2026 and January 2027.
| Where | When | What we are doing | What to expect |
|---|
Box Hill Gardens west | Day works: Ongoing until late January 2027
| - Building open space enhancements
| - Up to 10 car spaces closed on Nelson Road between Arnold Street and Whitehorse Road
- Low levels of noise, dust and vibration
|
|
Whitehorse Road and Station Street, Box Hill
| Day works: Ongoing Night works: From December at times | - Moving and decommissioning services
- Demolition of structures
- Tree and vegetation removal
| - Westbound and eastbound lane closures between Nelson Road and Station Street
- Northbound lane closure between Whitehorse Road and Main Street
- Moderate levels of noise, dust and vibration
|
|
SRL worksites, Box Hill
| Day works: Ongoing
| - Demolition of structures
- Safely removing hazardous material
- Tree and vegetation removal
- Moving and decommissioning services
- Site investigations and establishment
- Installing temporary lighting
| - Truck movements and oversized deliveries
- Moderate to high levels of noise, dust and vibration
|
|
Irving Avenue & Elland Avenue, Box Hill
| Day works: Ongoing | - Site investigations
- Moving and decommissioning services
- Building a new access road between Irving Avenue and Whitehorse Road
| - Lane closures at times
- Property access maintained
- Up to 10 car spaces closed on Irving Avenue at times
- Low levels of noise, dust and vibration
|
|
Market Street & Main Street, Box Hill
| Day works: Ongoing
Night works: From December at times
| - Moving and decommissioning services
- Tree and vegetation removal
| - Changed access and closures of Market Street pedestrian crossing day and night at times
- Moderate levels of noise, dust and vibration
|
|
Box Hill Gardens east
| Day works: Ongoing from mid January
| - Site investigations and establishment
- Moving and decommissioning services
- Tree and vegetation removal
| - Fencing, vehicles and machinery in the park
- Moderate levels of noise, dust and vibration
|
|
Hiltons Lane, Box Hill
| Day works: Ongoing from mid January
| | - Road closure
- Property access maintained
|
Holiday shutdown
There will be no SRL works during the holiday period from Wednesday 23 December 2026 to Tuesday 12 January 2027 inclusive at Box Hill.
.
Impacts
As with all major infrastructure projects, surrounding communities may experience some impacts during construction.
Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.
How we will manage our works
We will minimise impacts to the community by:
- Installing traffic and pedestrian detours
- Monitoring noise, dust and vibration levels
- Using noise blankets
- Using water and dust suppressants
Thank you for your patience and cooperation as we progress the delivery of SRL East at Box Hill.
Sign up for SMS notifications